CONTRACTOR PRACTICE EXAM WITH
ACTUAL CORRECT QUESTIONS AND
VERIFIED DETAILED ANSWERS
|CURRENTLY TESTING QUESTIONS AND
SOLUTIONS|ALREADY GRADED A+ |JUST
RELEASED!!|GUARANTEED PASS
1. In Ohio, a home improvement contract must be in writing when it is signed:
A. At the contractor’s office
B. At the consumer’s home
C. For commercial projects only
D. Only if over $10,000
Answer: B
Explanation: Under Ohio law, home solicitation sales (signed at the consumer’s residence)
must be written contracts to protect consumers.
2. A valid Ohio home improvement contract must include:
A. Contractor’s logo
B. Start and completion dates
C. Only the final price
D. Verbal promises
Answer: B
Explanation: Ohio requires clear start and end dates so consumers know when work will
begin and be completed.
1|Page
,3. The Ohio Consumer Sales Practices Act (CSPA) protects:
A. Contractors
B. Suppliers only
C. Consumers from unfair or deceptive acts
D. Government agencies
Answer: C
Explanation: The CSPA prohibits misrepresentation, deception, and unfair practices in home
improvement transactions.
4. When must a contractor provide a 3-day cancellation notice?
A. For all contracts
B. When work exceeds $1,000
C. When contract is signed at consumer’s home
D. Only for roofing
Answer: C
Explanation: Home solicitation sales require a 3-business-day right to cancel under Ohio law.
5. If a consumer cancels within the legal time frame, the contractor must:
A. Ignore the notice
B. Start work anyway
C. Refund any payments promptly
D. Charge a penalty
2|Page
, Answer: C
Explanation: Failure to refund payments after cancellation is a violation of Ohio consumer
law.
6. Which is considered a deceptive act?
A. Written estimates
B. Honest advertising
C. Misrepresenting materials or scope
D. Using change orders
Answer: C
Explanation: False or misleading statements violate the CSPA.
7. Change orders must be:
A. Verbal
B. Optional
C. Written and agreed upon
D. Free
Answer: C
Explanation: Any change in price or scope must be documented in writing.
8. Abandoning a project without notice may result in:
A. No penalty
B. Breach of contract
C. Automatic approval
D. Bonus payment
3|Page
, Answer: B
Explanation: Leaving a job unfinished without cause is a breach of contract.
9. Advertising by contractors must be:
A. Exaggerated
B. Anonymous
C. Truthful and accurate
D. Optional
Answer: C
Explanation: False advertising violates Ohio consumer protection laws.
10. A mechanic’s lien may be filed when:
A. The homeowner refuses to pay for completed work
B. No work was performed
C. There was no agreement
D. Materials were unused
Answer: A
Explanation: Liens protect contractors when lawful work is completed and unpaid.
11. Workers’ compensation insurance is required when a contractor:
A. Works alone
B. Has employees
C. Is self-employed only
D. Works part-time
4|Page