Hierarchy of construction documents (least to most) - ✔✔Standard drawings, Standard specs,
|| || || || || || || || || || || ||
Supplemental specs, Plans, Special provisions, Special provisions copied notes
|| || || || || || || ||
Which construction documents details approved additions and revisions to the standard spec -
|| || || || || || || || || || || || ||
✔✔Supplemental specs ||
This ensures an adequate bond between the existing pavement surface and the new asphalt
|| || || || || || || || || || || || || ||
overlay so that slippage and delamination do not occur - ✔✔Tack coat
|| || || || || || || || || || ||
Which tack coat can be used prior to May and after September? - ✔✔Conventional
|| || || || || || || || || || || || ||
Which tack coat can be used year round, and must be used from May through September? -
|| || || || || || || || || || || || || || || || ||
✔✔Trackless
What is the range of proper tack coat application? (in gal/yd^2) - ✔✔.05 to .10
|| || || || || || || || || || || || || ||
Proper tack coat will leave a residual asphalt cement content ranging from approximately...? (in
|| || || || || || || || || || || || || ||
gal/yd^2) - ✔✔.04 to .06 || || || ||
Most asphalt emulsions contain __% to __% residual asphalt cement - ✔✔60, 65
|| || || || || || || || || || || ||
Most asphalt emulsions contain __% to __% water - ✔✔35, 40
|| || || || || || || || || ||
When is a prime tack coat required? - ✔✔When required by the contract
|| || || || || || || || || || || ||
solutions
Hierarchy of construction documents (least to most) - ✔✔Standard drawings, Standard specs,
|| || || || || || || || || || || ||
Supplemental specs, Plans, Special provisions, Special provisions copied notes
|| || || || || || || ||
Which construction documents details approved additions and revisions to the standard spec -
|| || || || || || || || || || || || ||
✔✔Supplemental specs ||
This ensures an adequate bond between the existing pavement surface and the new asphalt
|| || || || || || || || || || || || || ||
overlay so that slippage and delamination do not occur - ✔✔Tack coat
|| || || || || || || || || || ||
Which tack coat can be used prior to May and after September? - ✔✔Conventional
|| || || || || || || || || || || || ||
Which tack coat can be used year round, and must be used from May through September? -
|| || || || || || || || || || || || || || || || ||
✔✔Trackless
What is the range of proper tack coat application? (in gal/yd^2) - ✔✔.05 to .10
|| || || || || || || || || || || || || ||
Proper tack coat will leave a residual asphalt cement content ranging from approximately...? (in
|| || || || || || || || || || || || || ||
gal/yd^2) - ✔✔.04 to .06 || || || ||
Most asphalt emulsions contain __% to __% residual asphalt cement - ✔✔60, 65
|| || || || || || || || || || || ||
Most asphalt emulsions contain __% to __% water - ✔✔35, 40
|| || || || || || || || || ||
When is a prime tack coat required? - ✔✔When required by the contract
|| || || || || || || || || || || ||