Federal Emergency Management Agency (FEMA) IS 405 FINAL EXAM STUDY GUIDE 2026/2027 ACCURATE QUESTIONS WITH CORRECT DETAILED ANSWERS || 100% GUARANTEED PASS NEWEST VERSION 1. What is the purpose of the IS405 Project Management course? - ANSWER A. to establish a strong academic foundation and practical skills for managing projects in a fast-paced, often-changing environment; 2. B. to provide skills to Class Members that will assist them in their academic projects immediately 3. C. establish an environment of discussion and learning that supports the standards of the Gospel of Jesus Christ, enhancing the testimony or understanding of the Gospel 4. What is a WBS? - ANSWER The Work Breakdown Structure 5. There are five typical types of Major Components. Which of the following is NOT one of them? - ANSWER 1. Geography 2. Phase 3. Functional group 4. Release 5.Deliverable 6. There are three types of logical relationships(dependencies) that we identified that are most commonly used to create the Dependency Diagram. Which of the following is not one? - ANSWER Possible options: Start to start, finish to finish, finish to start 7. NOT start to finish! 8. When talking about task relationships, what does the word "lag" mean? - ANSWER The pause time between the two relationships. (That's not the verbatim answer.) 9. What is the first question you ask when forming the Planning Team? - ANSWER Which functions are most affected? 10. Which is the second question you ask when forming the Planning Team? - ANSWER Which functions contribute? 11. How many advocates (team members) should be on the Planning Team? - ANSWER 4-7 12. What is the first step in managing risk? - ANSWER Probably "Preventive Actions (mitigate likelihood)", but could be "identify risks" 13. According to Ernie's view, as discussed in class, who owns quality during a project? a. Project Manager b. Project Sponsor c. Functional Managers d. CEO - ANSWER c. Functional Managers 14. Which of the following is NOT a contributor to quality during a project? a. Norms and Standards of the organization b. Customer requirements c. Subject Matter Experts' input d. Employees' expertise and training e. All of the above contribute to quality! - ANSWER e. All of the above contribute to quality! 15. Regarding the Business Culture mapping, which of the following is NOT correct? (What is the 2x2?) - ANSWER (From Top Left in Clock-wise rotation) Collaboration (Customer Based) Control (Process/Efficiency) Competence (Product/Quality) Cultivation (Employee) 16. When determining who should be on the Planning Team, the Project Manager and Sponsor should ask specific questions. Choose the option below that has the right questions in the right order. - ANSWER 1. What/which functions are most affected by the success of the project? 2. Which functions will most contribute to the success of the project? Simplified: 1. Most affected by 2. Most contribute to 17. Managing the project is much easier, and much more reliable if . . . a. The Project Manager has carefully developed the project plan. b. The Planning Team has followed the steps of the process faithfully. c. The Sponsor has managed the plan development. d. Everyone just gets out of the way and lets the developers go to work. - ANSWER b. The Planning Team has followed the steps of the process faithfully. 18. Think about the "silver bullets" to getting good estimates. Which of the following statements is NOT accurate? (What are the silver bullets?) - ANSWER 1. Timing = estimate in context (Don't ask for an estimate until you see the dependency-diagram) 3. Size = break it down to a recognizable effort/level 4. Estimator = get the right person making the estimate (first doer, but if no doer then project manager/owner) 19. What is a critical task? - ANSWER - A task that is on the Critical Path and does not have some amount of slack or float (from textbook pg.2-95) - Indicated in vertical red-dashed lines 20. What is a noncritical task? - ANSWER - A task that is not on the Critical Path and has some amount of slack or float (2-95) - Indicated in solid blue

Show more Read less
Institution
Federal Emergency Management Agency IS 405
Course
Federal Emergency Management Agency IS 405

Content preview

Federal Emergency Management Agency
(FEMA) IS 405 FINAL EXAM STUDY GUIDE
2026/2027 ACCURATE QUESTIONS WITH CORRECT
DETAILED ANSWERS || 100% GUARANTEED PASS
<NEWEST VERSION>


1. What is the purpose of the IS405 Project Management course? - ANSWER
✔ A. to establish a strong academic foundation and practical skills for
managing projects in a fast-paced, often-changing environment;


2. B. to provide skills to Class Members that will assist them in their academic
projects immediately


3. C. establish an environment of discussion and learning that supports the
standards of the Gospel of Jesus Christ, enhancing the testimony or
understanding of the Gospel


4. What is a WBS? - ANSWER ✔ The Work Breakdown Structure


5. There are five typical types of Major Components. Which of the following is
NOT one of them? - ANSWER ✔ 1. Geography
2. Phase
3. Functional group
4. Release
5.Deliverable

,6. There are three types of logical relationships(dependencies) that we
identified that are most commonly used to create the Dependency Diagram.
Which of the following is not one? - ANSWER ✔ Possible options: Start to
start, finish to finish, finish to start
7. NOT start to finish!


8. When talking about task relationships, what does the word "lag" mean? -
ANSWER ✔ The pause time between the two relationships. (That's not the
verbatim answer.)


9. What is the first question you ask when forming the Planning Team? -
ANSWER ✔ Which functions are most affected?


10.Which is the second question you ask when forming the Planning Team? -
ANSWER ✔ Which functions contribute?


11.How many advocates (team members) should be on the Planning Team? -
ANSWER ✔ 4-7


12.What is the first step in managing risk? - ANSWER ✔ Probably "Preventive
Actions (mitigate likelihood)", but could be "identify risks"


13.According to Ernie's view, as discussed in class, who owns quality during a
project?


a. Project Manager
b. Project Sponsor
c. Functional Managers
d. CEO - ANSWER ✔ c. Functional Managers

,14.Which of the following is NOT a contributor to quality during a project?


a. Norms and Standards of the organization
b. Customer requirements
c. Subject Matter Experts' input
d. Employees' expertise and training
e. All of the above contribute to quality! - ANSWER ✔ e. All of the
above contribute to quality!


15.Regarding the Business Culture mapping, which of the following is NOT
correct? (What is the 2x2?) - ANSWER ✔ (From Top Left in Clock-wise
rotation)


Collaboration (Customer Based)


Control (Process/Efficiency)


Competence (Product/Quality)


Cultivation (Employee)


16.When determining who should be on the Planning Team, the Project
Manager and Sponsor should ask specific questions. Choose the option
below that has the right questions in the right order. - ANSWER ✔ 1.
What/which functions are most affected by the success of the project?
2. Which functions will most contribute to the success of the project?


Simplified:

, 1. Most affected by
2. Most contribute to


17.Managing the project is much easier, and much more reliable if . . .


a. The Project Manager has carefully developed the project plan.
b. The Planning Team has followed the steps of the process faithfully.
c. The Sponsor has managed the plan development.
d. Everyone just gets out of the way and lets the developers go to work. -
ANSWER ✔ b. The Planning Team has followed the steps of the
process faithfully.


18.Think about the "silver bullets" to getting good estimates. Which of the
following statements is NOT accurate? (What are the silver bullets?) -
ANSWER ✔ 1. Timing = estimate in context (Don't ask for an estimate until
you see the dependency-diagram)


3. Size = break it down to a recognizable effort/level


4. Estimator = get the right person making the estimate (first doer, but if no
doer then project manager/owner)


19.What is a critical task? - ANSWER ✔ - A task that is on the Critical Path
and does not have some amount of slack or float (from textbook pg.2-95)


- Indicated in vertical red-dashed lines


20.What is a noncritical task? - ANSWER ✔ - A task that is not on the Critical
Path and has some amount of slack or float (2-95)

Written for

Institution
Federal Emergency Management Agency IS 405
Course
Federal Emergency Management Agency IS 405

Document information

Uploaded on
January 5, 2026
Number of pages
41
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

$14.99
Get access to the full document:

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
ProfBenjamin Havard School
Follow You need to be logged in order to follow users or courses
Sold
647
Member since
1 year
Number of followers
17
Documents
3863
Last sold
20 hours ago
EXCELLENT ACHIEVERS LIBRARY

As a professional tutor, I provide exceptional assistance with homework, quizzes, and exams across various subjects, including Psychology, Nursing, Biological Sciences, Business, Engineering, Human Resource Management, and Mathematics. I am dedicated to offering high-quality support and ensuring that all work meets scholarly standards. To enhance the effectiveness of our services, I work with a team of experienced tutors to create comprehensive and effective revision materials. Together, we are committed to helping students achieve excellent grades through our collaborative efforts and expertise.

Read more Read less
3.8

135 reviews

5
63
4
18
3
33
2
9
1
12

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions