TEST BANK QUESTIONS AND ANSWERS 2025
1. What is the primary purpose of the project charter?
A. To define project deliverables
B. To formally authorize the project and assign the project manager
C. To schedule project activities
D. To create the work breakdown structure (WBS)
Correct Answer: B
Explanation: The project charter is issued by the sponsor and authorizes the project, giving the
project manager authority to apply organizational resources.
2. Which of the following best defines a project?
A. A set of ongoing operations
B. A temporary endeavor undertaken to create a unique product, service, or result
C. Routine work performed daily
D. A recurring business process
Correct Answer: B
Explanation: Projects are temporary and unique, unlike operational activities that are
continuous.
,WGU C722 PROJECT MANAGEMENT EXAM
TEST BANK QUESTIONS AND ANSWERS 2025
3. Which process group includes activities to define and refine objectives and select the best
course of action?
A. Initiating
B. Planning
C. Executing
D. Monitoring and Controlling
Correct Answer: B
Explanation: Planning processes establish the total scope, refine objectives, and develop the
course of action required to attain those objectives.
4. What is the purpose of the Work Breakdown Structure (WBS)?
A. To define project risks
B. To identify resource needs
C. To decompose project deliverables into smaller, manageable components
D. To assign team roles
Correct Answer: C
Explanation: The WBS organizes and defines the total scope of the project by breaking
deliverables into smaller tasks.
,WGU C722 PROJECT MANAGEMENT EXAM
TEST BANK QUESTIONS AND ANSWERS 2025
5. Which knowledge area includes processes for managing the timely completion of the project?
A. Project Scope Management
B. Project Schedule Management
C. Project Cost Management
D. Project Integration Management
Correct Answer: B
Explanation: Project Schedule Management deals with planning, estimating, and controlling the
schedule.
6. The document that outlines how changes will be managed and controlled is called the:
A. Change request form
B. Change management plan
C. Issue log
D. Configuration management plan
Correct Answer: B
Explanation: The change management plan defines the process for requesting, evaluating, and
approving changes.
7. What is the main output of the “Identify Stakeholders” process?
A. Stakeholder Register
, WGU C722 PROJECT MANAGEMENT EXAM
TEST BANK QUESTIONS AND ANSWERS 2025
B. Project Charter
C. Risk Register
D. Communication Plan
Correct Answer: A
Explanation: The stakeholder register lists all project stakeholders, their interests, and levels of
influence.
8. Which project management process group occurs at the start of the project lifecycle?
A. Executing
B. Planning
C. Initiating
D. Closing
Correct Answer: C
Explanation: The initiating phase defines the project’s purpose and formally authorizes it.
9. What is the critical path in a project?
A. The path with the shortest duration
B. The sequence of tasks that determines the project’s minimum duration
C. Tasks that can be delayed without affecting the end date
D. The path with the least cost