CON 367 CERTIFICATION EVALUATION EXAMS
2026 QUESTIONS WITH ANSWERS
◉T/F: In the Contractor Quality Control (CQC) Inspection process
implemented by some federal agencies, the Contractor must organize
and maintain an inspection system . Answer: True
◉T/F: In fast-track projects with multiple contractors, the services of a
professional construction management firm (agency cm) are essential .
Answer: True
◉A professional construction management firm (agency cm) can
participate in what phases of a project? . Answer: Conception, program
planning, design, construction, and closeout
◉T/F: The design-build process may face some legal barriers when tried
to be implemented in the public sector. . Answer: True
◉T/F: On a multiple-prime project, the owner is responsible for
coordinating the various trade contractors with whom it has contracted. .
Answer: True
, ◉T/F: The Resident Project Representative should not direct the
Contractor's work . Answer: True
◉Which of the following is under the authority of the Resident Project
Representative?
A) to approve materials and workmanship that meet the contract
requirements
B) to require the Contractor to furnish more than that required by the
plans and specs
C) to approve deviations from the contract requirements
D) to order the contractor to stop operations . Answer: A) to approve
materials and workmanship that meet the contract requirements
◉In what order do submittals from the subcontractor get to the designer?
. Answer: 1- subcontractor
2-general contractor
3-resident project representative
4-project manager
5-design reviewers
◉T/F: The resident project representative should obtain the contract
documents and study those as soon as being engaged to provide resident
inspection on a project. . Answer: True
2026 QUESTIONS WITH ANSWERS
◉T/F: In the Contractor Quality Control (CQC) Inspection process
implemented by some federal agencies, the Contractor must organize
and maintain an inspection system . Answer: True
◉T/F: In fast-track projects with multiple contractors, the services of a
professional construction management firm (agency cm) are essential .
Answer: True
◉A professional construction management firm (agency cm) can
participate in what phases of a project? . Answer: Conception, program
planning, design, construction, and closeout
◉T/F: The design-build process may face some legal barriers when tried
to be implemented in the public sector. . Answer: True
◉T/F: On a multiple-prime project, the owner is responsible for
coordinating the various trade contractors with whom it has contracted. .
Answer: True
, ◉T/F: The Resident Project Representative should not direct the
Contractor's work . Answer: True
◉Which of the following is under the authority of the Resident Project
Representative?
A) to approve materials and workmanship that meet the contract
requirements
B) to require the Contractor to furnish more than that required by the
plans and specs
C) to approve deviations from the contract requirements
D) to order the contractor to stop operations . Answer: A) to approve
materials and workmanship that meet the contract requirements
◉In what order do submittals from the subcontractor get to the designer?
. Answer: 1- subcontractor
2-general contractor
3-resident project representative
4-project manager
5-design reviewers
◉T/F: The resident project representative should obtain the contract
documents and study those as soon as being engaged to provide resident
inspection on a project. . Answer: True