⩥ The master data relevant to the production process are
A. Work Centers
B. Material Masters
C. Bill of Materials
D. Client
E. Company Code. Answer: A
B
C
⩥ Which of the following are statuses that can apply to a BOM?
A. On
B. Off
C. Active
D. Inactive
E. Open. Answer: C
D
, ⩥ What are the basic time elements in the production process?
A. Setup Time
B. Alternate time
C. Build Time
D. Teardown time
E. Processing time. Answer: A
D
E
⩥ Which of the following can be included in processing time?
A. Machine time
B. Configuring work center
C. Configuring equipment
D. Labor Time
E. Setup Time. Answer: A
D
⩥ Which of the following are the general classifications of time
elements in production?
A. Floating
B. Volatile
C. Fixed