Advanced Rigger Exam Questions with Answers
1. What is meant by the term "two blocking"?: The load block contacts the boom point sheaves.
2. Lifting 20,000 lbs with a 2-leg bridle sling at a 30°horizontal sling angle, what is the
force applied to each leg?: 20,000 pounds
3. In multiple crane lifts using an equalizer beam, the weight of the beam should be
considered:: Part of the load weight
4. What is required if there is a deviation from the lift plan?: A new lift plan
5. On level ground using skids and rollers, what percent of the weight of the load
should yield the required line pull asa general rule of thumb?: 5%
6. All of the following are results of unbalanced reeving of the hook block EXCEPT::
Wear on the hook
7. Before a spreader bar or beams can be used they MUST have been:: Tested and approved
8. When materials are being hoisted to an upper level, a tag line is used to:: Help control the load
9. Two cranes are lifting 100 tons.If crane A has 40% of the load, how much weight will
crane B have on its hook?: 120,000 lbs
10. To CONFIRM the rated capacity of a specific sling, consult the manufactur- er's::
Sling tag
11. . OSHA regulations require hook replacement if the opening exceeds what
percentage of its original throat opening?: 15%
12. At what percentage of increase in length should a chain sling be removed from
1/
5
, service?: 5%
13. The methodical process that attempts to identify hazards and devise plans to
overcome or eliminate hazards which may interfere with crane or rigging is called:: Lift plan
14. What provides additional control of a load being lifted?: Tag lines
15. When traveling on a rubber tire mobile crane, how should the boom be
positioned?: In line with the direction of travel
16. Before performing pick and carry operations with any mobile crane, it is
important to:: Refer to the manufacturer's capacity chart
17. According to ASMEB30.5, a two crane lift is signaled by:: One designated person
18. What is the PRIMARY concern when working with high boom angles?: Backward stability
19. On multiple crane lifts, the load on each crane should NOT exceed what
percentage of capacity?: 75%
20. What are lifting lugs?: Eyelets welded to a steel plate for lifting
21. The formula for determining stress on a snatch block performing a vertical lift is:
line pull x block factor = block load. What must be done to calculate formula?: Multiply the load
weight by the coefficient of friction to determine line pull, and then use the standard formula
22. If both fists are placed in front of your body with your thumbs pointed
outward, the crane operator should:: Extend the boom sections
23. What is the MAXIMUM percent of the rated capacity of a crane that can be used
to lift personnel?: 50%
24. When does lightening present the greatest hazard to the crane and rigging
personnel?: When thunder and lightning are apparent
2/
5
1. What is meant by the term "two blocking"?: The load block contacts the boom point sheaves.
2. Lifting 20,000 lbs with a 2-leg bridle sling at a 30°horizontal sling angle, what is the
force applied to each leg?: 20,000 pounds
3. In multiple crane lifts using an equalizer beam, the weight of the beam should be
considered:: Part of the load weight
4. What is required if there is a deviation from the lift plan?: A new lift plan
5. On level ground using skids and rollers, what percent of the weight of the load
should yield the required line pull asa general rule of thumb?: 5%
6. All of the following are results of unbalanced reeving of the hook block EXCEPT::
Wear on the hook
7. Before a spreader bar or beams can be used they MUST have been:: Tested and approved
8. When materials are being hoisted to an upper level, a tag line is used to:: Help control the load
9. Two cranes are lifting 100 tons.If crane A has 40% of the load, how much weight will
crane B have on its hook?: 120,000 lbs
10. To CONFIRM the rated capacity of a specific sling, consult the manufactur- er's::
Sling tag
11. . OSHA regulations require hook replacement if the opening exceeds what
percentage of its original throat opening?: 15%
12. At what percentage of increase in length should a chain sling be removed from
1/
5
, service?: 5%
13. The methodical process that attempts to identify hazards and devise plans to
overcome or eliminate hazards which may interfere with crane or rigging is called:: Lift plan
14. What provides additional control of a load being lifted?: Tag lines
15. When traveling on a rubber tire mobile crane, how should the boom be
positioned?: In line with the direction of travel
16. Before performing pick and carry operations with any mobile crane, it is
important to:: Refer to the manufacturer's capacity chart
17. According to ASMEB30.5, a two crane lift is signaled by:: One designated person
18. What is the PRIMARY concern when working with high boom angles?: Backward stability
19. On multiple crane lifts, the load on each crane should NOT exceed what
percentage of capacity?: 75%
20. What are lifting lugs?: Eyelets welded to a steel plate for lifting
21. The formula for determining stress on a snatch block performing a vertical lift is:
line pull x block factor = block load. What must be done to calculate formula?: Multiply the load
weight by the coefficient of friction to determine line pull, and then use the standard formula
22. If both fists are placed in front of your body with your thumbs pointed
outward, the crane operator should:: Extend the boom sections
23. What is the MAXIMUM percent of the rated capacity of a crane that can be used
to lift personnel?: 50%
24. When does lightening present the greatest hazard to the crane and rigging
personnel?: When thunder and lightning are apparent