All submittals for government approval must be provided by the
in time to allow for the review, approval,
procurement, delivery, and performance of preparatory phase for an
item before it is needed for construction. - ✔✔✔ Correct Answer >
Contractor to the Government
The is workmanship oriented, and where
workmanship standards are established. - ✔✔✔ Correct Answer >
Initial phase
Contractor testing procedures: - ✔✔✔ Correct Answer > Are
outlined in the Quality Control Plan as defined by Section
01450N/01451A and addressed at the Coordination and Mutual
Understanding Meeting (Navy).
Requests for information are submitted to: - ✔✔✔ Correct Answer >
Ask for clarification of the contract
, The contract requires the contractor to submit quality control reports: -
✔✔✔ Correct Answer > Daily.
The means for enforcing contract compliance are provided in the: -
✔✔✔ Correct Answer > Contract clauses of the contract.
ENG Form 4288-R, the submittal register: - ✔✔✔ Correct Answer >
Identifies those submittals requiring government approval
The primary purpose of the Three-Phase control system is to: - ✔✔✔
Correct Answer > Require the contractor to plan and schedule his
work.
The contractor is required to conduct a preparatory phase meeting
before he begins any definable feature of work except when: - ✔✔✔
Correct Answer > There are no exceptions to the rule.
The is the appropriate time to assure that all
materials and/or equipment have been tested, submitted, and
approved. - ✔✔✔ Correct Answer > Preparatory phase
The Quality Control report should address: - ✔✔✔ Correct Answer >
Both work completed and control activities