P-99 / Low PSI Oil Burner Operator Questions
and Answers 100% Solved
Save
Practice questions for this set
Learn 1 /7 Study with Learn
Terms in this set (115)
, All heating, combustion, and 170 ̊ F
cooking equipment shall be
provided with insulation or the
building construction shall be fire
protected, so that during operation
the surface of combustible
construction materials will not be
raised to a temperature higher than
____.
Acceptance tests: Boilers shall not Inspected and tested.
be placed in operation upon
completion of construction until they
have been ____ and an equipment use
permit has been issued by the
commissioner.
Periodic boiler inspections: All Once a year.
boilers shall be inspected at least ____
including chimney connections.
Owner's annual statement: The owner Written statement.
of each boiler that is subject to
periodic inspections shall file an
annual ____ with the commissioner,
specifying the location of each
boiler and arrangement for
inspection.
What three things must be tested for (1) Tightness of liquid fuel piping.
any fuel burning and storage
installation before the system can be (2) Tightness of fuel oil storage tanks.
operated?
(3) Tightness of gas distribution piping.