WGU C723 Exam Questions and Answers
Graded A+
Expected Completion Times Formula - Correct answer-A + 4m + p over 6
Expected Completion Times - A - Correct answer-optimistic
Expected Completion Times - M - Correct answer-probable
Expected Completion Times - P - Correct answer-pessimistic
Economic Order Quanitity Formula - Correct answer-Square root of 2dt over h or
ic
EOQ - D - Correct answer-annual demand
EOQ - T - Correct answer-cost to place order
EOQ - H - Correct answer-annual holding cost per unit
EOQ - I - Correct answer-interest rate
EOQ - C - Correct answer-per unit cost
Cost if Items Formula - Correct answer-purchase price x annual demand
©COPYRIGHT 2025, ALL RIGHTS RESERVED 1
Graded A+
Expected Completion Times Formula - Correct answer-A + 4m + p over 6
Expected Completion Times - A - Correct answer-optimistic
Expected Completion Times - M - Correct answer-probable
Expected Completion Times - P - Correct answer-pessimistic
Economic Order Quanitity Formula - Correct answer-Square root of 2dt over h or
ic
EOQ - D - Correct answer-annual demand
EOQ - T - Correct answer-cost to place order
EOQ - H - Correct answer-annual holding cost per unit
EOQ - I - Correct answer-interest rate
EOQ - C - Correct answer-per unit cost
Cost if Items Formula - Correct answer-purchase price x annual demand
©COPYRIGHT 2025, ALL RIGHTS RESERVED 1