What is one of the most significant aspects of PBL - ANSWER-
Negotiated Agreements between PMs, Force Providers, and
Support Providers. DoD Instruction 5000.2
What does the term Engineering relates to? - ANSWER-It relates
to building things
System Engineering Plan? - ANSWER-PMs shall prepare a
system engineering plan (SEP) for each milestone review,
beginning with milestone A
What are Joint Acquisition Programs? - ANSWER-Joint
Acquisition Programs is any acqusition system, subsystem,
component, or technology program with astrategy that includes
funding by more than one DoD component during any phase of a
system's life cycle.
,2|Page
Who decides to place programs under joint acquisition
management? - ANSWER-The MDA decides whether to place
programs under joint management and designates the lead
executive DoD component.
What law requires an analysis of potential opportunities of
international cooperation? - ANSWER-10 USC 2350a(e) requires
international cooperation consideration in the initial aquisition
strategy for a program.
When international programs may be established in the defense
acqusition program - ANSWER-Decision to include international
partners needs to be included during development of the initial
capabilities document but no early than the material and solution
analysis phase.
When is Earned Value Management (EVM) implemented -
ANSWER-EVM is part of program management . It ensures that
cost , schedule and technical aspects of the contract are truly
integrated.
,3|Page
In what type of contracts EVM is required - ANSWER-EVM is
required on Cost, and/or Incentive contracts valued at greater
than $20M.
What is EVM? - ANSWER-Earned Value Management is a tool
that
1. Relates the scope of the work to its associated budgets and
schedule.
2. Measures the work progress in objective terms
3. States that value of the work completed in dollars and other
measurable units.
What are EVM techniques? - ANSWER-Correlate the budgeted
cost of worked scheduled with the budget cost of work performed
(BCWP)
1. 0/100 Earned Value Technique
2. Percent Start/Percent Finish EV Technique (50/50) (25/75)
(80/20)
3. Percent Complete
4. Units Completed
, 4|Page
5. Equivalent Units
Describe the Percent Start/Percent Finish EV Technique -
ANSWER-Is an objective earned value technique tied to the start
and completion of a work package task, often referred to %
assigned to the start and finish milestone such as (50/50...)
Thsi technique tends to overstate performance in the first half of
the period of performance and uderstate performance in the last
half.
What is the most important step in EVM system? - ANSWER-Is
the establishment of the Performance Measurement Baseline
(PMB)or the Budgeted Cost of Work Schedule (BCWS)
What is the PMB in and EVM? - ANSWER-The PMB includes the
undistributed budget, all summary level planning package
budgets, and all control account budgets. It does not include
management reserve.