Answers (Latest 2026)
Change - Correct Answers ✅Also referred to as extras.
When owner makes them they become modification of
contract. If this impacts project cost/duration a change order
is required
Change Order - Correct Answers ✅Changes issued by the
owner that requires a change to the original contract. When
GC receives modification proposal- must evaluate the
potential impact the changes will have on the cost/duration,
subcontractors involved in change must also submit
quotations. If quotation is acceptable, GC will submit a
change order. Owner evaluates prices proposed by GC, then
issues a formal change order to GC at agreed price, or on a
cost-plus basis, or decides not to issue a change order.
Field Change - Correct Answers ✅Type of change that has
no impact on the contract's duration or amount. Authorized
by personnel in the field without owner approval. Typically,
minor, but are required to facilitate the construction effort.
Cardinal Change - Correct Answers ✅a change order that
is of such magnitude that the original scope of the project is
altered to an extent that constitutes a new contract
the owner, and the architect/engineer if the owner has
transferred to them the ability to take on that responsibility -
Correct Answers ✅Who has the authority to make a
change order?
, CMGT 3500 Test 3 Exam Questions and
Answers (Latest 2026)
Pre-bid site investigation - Correct Answers ✅Generally,
includes information in the form of boring logs and results of
tests on the indigenous soils, although may be an accurate
representation of the site, it is common practice to stipulate
that the contractor make an independent site visit and
investigation.
Differing Site Conditions - Correct Answers ✅2 broad
categories- the actual conditions differ materially or at
variance with the conditions indicated in the contract
documents. And the actual conditions are of an unusual
nature and differ materially or are at variance with what the
contractor should have reasonably anticipated- not
foreseeable.
Documentation - Correct Answers ✅When dealing with
changed conditions always use__________. Including photos,
labor costs, equipment costs, etc.
Whatever the contract states. Traditionally, contractor owns
the float but the contract will state exactly. - Correct
Answers ✅Who owns float?
Construction Schedules - Correct Answers ✅Show the
proposed sequence of work within the number of working
days set up in the contract. Often the owner may require that
this schedule be submitted before the pre-construction