PROCEDURES EXAM PRACTICE QUESTIONS
WITH CORRECT ANSWERS ACTUAL EXAM
PAPER 2026 COMPLETE SOLUTIONS
⩥ You are the contracting officer for a firm-fixed-price purchase order
for commercial services with a value of $1,425,000. Your customer has
notified you that one of the contractually required reports accepted by
the Government was submitted five days late. You investigate and verify
that the report was submitted late. Which one of the following
statements regarding the nonconforming performance is FALSE?
Answer: The Government must pay for reperformance of the
nonconforming service because the report was accepted
⩥ You are reviewing the requirements package for the purchase of lab
equipment for a health clinic that does not exceed the SAT. It must be
compatible with the equipment currently being used at the clinic. This is
essential in meeting the agency's needs. Market research identified only
one manufacturer able to meet the requirement for compatible
equipment. Which one of the following is correct regarding the policies
for describing your agency's needs? Answer: The basis for not providing
for maximum competition must be documented in the contract file.
⩥ Which one of the following statements about solicitations using SAP
is correct? Answer: The basis on which award will be made must be
stated.
, Stating the relative importance assigned to each evaluation factor is not
required.
Buyers are encouraged to use best value
⩥ Which one of the following is NOT a mandatory Government source
for satisfying a supply requirement? Answer: Commercial sources
⩥ You have a requirement for a new contract for grounds maintenance at
your military installation. The Base Commander has expressed the need
for clearly stated performance objectives, as the current contractor
performing the services is not meeting the Commander's expectations.
Consistent with the order of precedence for requirements documents,
which one of the following documents would be included in the new
contract? Answer: A Performance Work Statement (PWS)
⩥ You are the contracting officer for a commercial services requirement
with an estimated value of $2,600,000. None of the exceptions in FAR
5.202 apply. Which one of the following correctly describes the
requirement for publicizing this proposed contract action? Answer:
Notice of the proposed action must be transmitted to the GPE.
⩥ You have a requirement for administrative support with an estimated
value of $1,500,000. Market research shows there are numerous