EXAC Study Cards - Section 4 Questions
and Correct Answers/ Latest Update /
Already Graded
To reply lien claimant on info request
Ans: 21
Cross-examination notice for lien claimsnt
Ans: 7
Preservation of lien
Ans: 45
Perfection of lien
Ans: 45
Expiry of lien from perfection action
Ans: 2 years
To reply to application for Substantial
All rights reserved © 2025/ 2026 |
, Page |2
Ans: 10+7
To reply to application for Certificate Statement of completion
Ans: 10+7
To pay after issuance of certificate of completion
Ans: 5
To pay holback
Ans: 45 from a) publish in newspaper, b) completion of
contract, or c) contract is abandoned
Mail notice
Ans: 5 excl. Holidays
Email notice
Ans: 0 (only working hours)
2% interest on delayed payments
All rights reserved © 2025/ 2026 |
, Page |3
Ans: 60
4% interest on delayed payments
Ans: Per annum, after 60 days
Submit Schedule of values prior to first application for payment
Ans: 15
To reply to application for typical payment
Ans: 10
Owner to pay typical payment
Ans: 20 from a) application for payment, or b) last day of
monthly payment period
Owner to deposit holdback monies in joint account
Ans: 10 before end of holdback period
To give notice of concealed conditions
All rights reserved © 2025/ 2026 |
, Page |4
Ans: 5
To give notice of delays outside owner/arch. Fault
Ans: 10 (and no extra money!)
Architect to decide on claim for a change in price
Ans: 30
GC to act on owner's termination notice
Ans: 5
GC right to terminate work due to delays
Ans: 20
to act on GC's termination notice
Ans: 5
Termination of Broad Form insurance(from start work date)
All rights reserved © 2025/ 2026 |