WMGT 322 Exam with verified detailed solutions || || || || || ||
(From the Initial Stages of Project Development) Which of the following could be
|| || || || || || || || || || || || ||
considered stakeholders for a Civil Engineer project? Select ALL that apply. -
|| || || || || || || || || || || ||
✔✔Contracting Officer ||
Facility User ||
Communications Squadron Representative || ||
|| Airfield Manager ||
(From the Initial Stages of Project Development) Which of the following documents could
|| || || || || || || || || || || || ||
be considered part of the project record? Select ALL that apply. - ✔✔Independent
|| || || || || || || || || || || || ||
Government Estimate ||
|| Quality Control Plan || ||
|| Contractor Submittals ||
(From the Initial Stages of Project Development) A SABER contractor submits a project
|| || || || || || || || || || || || ||
invoice to the government that includes rental of a 25K Forklift. The construction inspector
|| || || || || || || || || || || || || ||
for this project clearly recalls that the only forklift used on the jobsite was a smaller 5K
|| || || || || || || || || || || || || || || || ||
forklift, which costs significantly less money to rent. Which document in the project record
|| || || || || || || || || || || || || ||
could be used to dispute this claim? - ✔✔AF Form 1477 Daily Construction Inspection
|| || || || || || || || || || || || || ||
Report
(From the Programming Fundamentals Lesson) You are working on a project and
|| || || || || || || || || || || ||
determine a change order is needed because the beams were too small to handle the roof
|| || || || || || || || || || || || || || || ||
load. However, this would exceed the approval authority for this Construction project. What
|| || || || || || || || || || || ||
is a viable option for the project team? - ✔✔Resubmit the project to obtain appropriate
|| || || || || || || || || || || || || || || ||
approval even if work must stop while the approval is obtained.
|| || || || || || || || || ||
, 2
(From the Programming Fundamentals Lesson) If a project modifies an existing facility to
|| || || || || || || || || || || || ||
make it compliant with current codes and regulations, it is likely a(n) _______ project. -
|| || || || || || || || || || || || || || ||
✔✔Repair
(From the Programming Fundamentals Lesson) Match the class of cost estimate with its
|| || || || || || || || || || || || ||
definition and use (not all options will have a match). - ✔✔Class 1: Unit Price
|| || || || || || || || || || || || || ||
Used to negotiate and compare bids with Contractors.
|| || || || || || ||
Class 3: Parametric Used for budgeting and making the official Programmed Amount.
|| || || || || || || || || || ||
Class 5: Square Foot Used for long range planning when the scope is still poorly defined.
|| || || || || || || || || || || || || || ||
(From the Programming Fundamentals Lesson) Determining the Work Classification is one
|| || || || || || || || || || ||
of the most important steps in the programming process, before determining the Fund
|| || || || || || || || || || || || ||
Source and Program Avenue. Work Classification can be defined as: - ✔✔Describing the
|| || || || || || || || || || || || ||
nature of the work to be accomplished
|| || || || || ||
(From the Project Management Plan Lesson) Who is responsible for creating a Project
|| || || || || || || || || || || || ||
Management Plan? - ✔✔Project Manager || || || ||
(From the Project Management Plan Lesson) At what phase in the Air Force project
|| || || || || || || || || || || || || ||
lifecycle should a Project Management Plan be developed? - ✔✔Planning and Programming
|| || || || || || || || || || ||
(From the Project Management Plan Lesson) MSgt Jones is an extremely competent SNCO
|| || || || || || || || || || || || ||
that has years of experience working on high voltage power projects. You have recently
|| || || || || || || || || || || || || ||
been appointed project manager for a new power line installation on a remote part of your
|| || || || || || || || || || || || || || || ||
base. Gaining MSgt Jones onto your project team would be an example of which type of
|| || || || || || || || || || || || || || || ||
risk? - ✔✔Opportunity
|| ||
WMGT 322 Exam with verified detailed solutions || || || || || ||
(From the Initial Stages of Project Development) Which of the following could be
|| || || || || || || || || || || || ||
considered stakeholders for a Civil Engineer project? Select ALL that apply. -
|| || || || || || || || || || || ||
✔✔Contracting Officer ||
Facility User ||
Communications Squadron Representative || ||
|| Airfield Manager ||
(From the Initial Stages of Project Development) Which of the following documents could
|| || || || || || || || || || || || ||
be considered part of the project record? Select ALL that apply. - ✔✔Independent
|| || || || || || || || || || || || ||
Government Estimate ||
|| Quality Control Plan || ||
|| Contractor Submittals ||
(From the Initial Stages of Project Development) A SABER contractor submits a project
|| || || || || || || || || || || || ||
invoice to the government that includes rental of a 25K Forklift. The construction inspector
|| || || || || || || || || || || || || ||
for this project clearly recalls that the only forklift used on the jobsite was a smaller 5K
|| || || || || || || || || || || || || || || || ||
forklift, which costs significantly less money to rent. Which document in the project record
|| || || || || || || || || || || || || ||
could be used to dispute this claim? - ✔✔AF Form 1477 Daily Construction Inspection
|| || || || || || || || || || || || || ||
Report
(From the Programming Fundamentals Lesson) You are working on a project and
|| || || || || || || || || || || ||
determine a change order is needed because the beams were too small to handle the roof
|| || || || || || || || || || || || || || || ||
load. However, this would exceed the approval authority for this Construction project. What
|| || || || || || || || || || || ||
is a viable option for the project team? - ✔✔Resubmit the project to obtain appropriate
|| || || || || || || || || || || || || || || ||
approval even if work must stop while the approval is obtained.
|| || || || || || || || || ||
, 2
(From the Programming Fundamentals Lesson) If a project modifies an existing facility to
|| || || || || || || || || || || || ||
make it compliant with current codes and regulations, it is likely a(n) _______ project. -
|| || || || || || || || || || || || || || ||
✔✔Repair
(From the Programming Fundamentals Lesson) Match the class of cost estimate with its
|| || || || || || || || || || || || ||
definition and use (not all options will have a match). - ✔✔Class 1: Unit Price
|| || || || || || || || || || || || || ||
Used to negotiate and compare bids with Contractors.
|| || || || || || ||
Class 3: Parametric Used for budgeting and making the official Programmed Amount.
|| || || || || || || || || || ||
Class 5: Square Foot Used for long range planning when the scope is still poorly defined.
|| || || || || || || || || || || || || || ||
(From the Programming Fundamentals Lesson) Determining the Work Classification is one
|| || || || || || || || || || ||
of the most important steps in the programming process, before determining the Fund
|| || || || || || || || || || || || ||
Source and Program Avenue. Work Classification can be defined as: - ✔✔Describing the
|| || || || || || || || || || || || ||
nature of the work to be accomplished
|| || || || || ||
(From the Project Management Plan Lesson) Who is responsible for creating a Project
|| || || || || || || || || || || || ||
Management Plan? - ✔✔Project Manager || || || ||
(From the Project Management Plan Lesson) At what phase in the Air Force project
|| || || || || || || || || || || || || ||
lifecycle should a Project Management Plan be developed? - ✔✔Planning and Programming
|| || || || || || || || || || ||
(From the Project Management Plan Lesson) MSgt Jones is an extremely competent SNCO
|| || || || || || || || || || || || ||
that has years of experience working on high voltage power projects. You have recently
|| || || || || || || || || || || || || ||
been appointed project manager for a new power line installation on a remote part of your
|| || || || || || || || || || || || || || || ||
base. Gaining MSgt Jones onto your project team would be an example of which type of
|| || || || || || || || || || || || || || || ||
risk? - ✔✔Opportunity
|| ||