Geschreven door studenten die geslaagd zijn Direct beschikbaar na je betaling Online lezen of als PDF Verkeerd document? Gratis ruilen 4,6 TrustPilot
logo-home
Tentamen (uitwerkingen)

APM PMQ EXAM QUESTIONS AND ANSWERS 2026

Beoordeling
-
Verkocht
-
Pagina's
59
Cijfer
A+
Geüpload op
26-01-2026
Geschreven in
2025/2026

APM PMQ EXAM QUESTIONS AND ANSWERS 2026

Instelling
Vak

Voorbeeld van de inhoud

APM PMQ EXAM LATEST
What is cost variance? what does a negative value mean? - ANSWERS-
The earned value minus the actual cost. negative value means the actual
cost is higher (over budget)


what is schedule variance? what does a negative value mean? -
ANSWERS-earned value minus planned costs. a negative one means
project is running behind


CPI formula, meanings of over or under 1 - ANSWERS-EV/AC
-CPI <1 : will be over budget
-CPI>1: will be under budget


SPI formula - ANSWERS-EV/PC
-SPI <1 : will be late
-SPI >1: will be early


Efficiency formula - ANSWERS-CPI * 100%


Final Cost/EAC - ANSWERS-Budget at Completion/CPI


Final Duration - ANSWERS-Planned Duration/SPI
END OF
PAGE 1

, APM PMQ EXAM LATEST

%complete - ANSWERS-(EV/BAC)*100


explain the stages in risk management - ANSWERS--initiate: understand
project objectives/priorities and define risk mgt approach
-identify risks: clearly define risks (cause/uncertainty/effect)
-assess/analyze risks: assign owner, understand probability and impact
on TCQ, use risk register to determine which risks should be mitigated
-plan responses: justify cost of action/inaction, effect on TCQ, residual
and 2ry risk
-implement resources: plan and resource
-monitor and control: is it working? updates from risk owners,
stakeholder updates


what are some risk identification techniques - ANSWERS--lessons
learned from other projects/phases
-assumptions analysis: test their stability (how sure you are they correct)
and sensitivity (how sensitive is project to them being incorrect)
-workshops(brainstorming, SWOT)
-prompt lists such as PESTLE
-checklists: detailed sets of questions

END OF
PAGE 2

, APM PMQ EXAM LATEST
-interviews
-delphi: experts review, summarize, distribute, revise opinion,
summarize distribute)


explain the responses to threats in risk management - ANSWERS--
accept: tolerate risk, monitor situation
-avoid: do something different
-reduce: modify plans to reduce severity
-transfer: insurance, transfer risk contractually e.g, via damages
-fallback: prep contingency plans, identify triggers


explain planning strategies for opportunities - ANSWERS--reject: don't
pursue
-exploit: pursue opp, make it happen
-enhance: increase probability/impact
-share: share contractually
-plan an option: what do if project develops in a certain way


roles of risk owners - ANSWERS--risk actionees
-assign resources

END OF
PAGE 3

, APM PMQ EXAM LATEST
-put mitigation action in plan and update schedule, WBS, cashflow etc
-update the risk register


explain some benefits of risk management - ANSWERS--improved
planning: higher success likely
-better contracts
-lower chance of accepting unsound projects
-increases stakeholder confidence
-more meaningful assessment of contingencies
-more objective comparison of possibilities
-continued build up of stats
-improved team spirit
-responsible approach to customers
-develops staff ability (can become risk champions)


what are issues and issue management - ANSWERS--problem that is
now breaching or about to breach delegated tolerances for the
project/program work


what is the difference between a risk, concern/problem, issue? -
ANSWERS--risk: something that has uncertainty
END OF
PAGE 4

Geschreven voor

Vak

Documentinformatie

Geüpload op
26 januari 2026
Aantal pagina's
59
Geschreven in
2025/2026
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

$18.49
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
Teacher101 Teachme2-tutor
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
472
Lid sinds
2 jaar
Aantal volgers
74
Documenten
10486
Laatst verkocht
2 dagen geleden

Quality is my middle name.....100% ...my policy is to create and nurture people of quality by continuous education and training.....i guaranteed good grades 100% Feel free to get in touch through inbox...anything regarding help or issue with the exams posted... Finally after purchase please leave a good rating if satisfied with my work.... All the best as we continue working to improve ourselves through education

4.6

274 beoordelingen

5
222
4
15
3
26
2
3
1
8

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen