Quiz_________________?
A contractor pays a workers' compensation rate of $0.08 per $100 of office employee
payroll, $0.15 per $100 of field supervisor payroll, and $0.26 per $100 of field employee
payroll. Total office employee payroll for the year is $25,000. Total field supervisor payroll is
$48,000. Total field employee payroll is $225,000. The contractor receives a discount of 5%
of total premiums for having a safety program in place. The total workers' compensation for
the year is... -
Answer✅
More than $600
Quiz_________________?
A contractor puts in a claim under a comprehensive standard general liability policy. The
policy has no additional coverage, riders, or floaters, and has a $500 deductible per
occurrence. The claim is for a job-site accident that caused $2,000 of injuries to employees,
$1,800 of injuries to a pedestrian, $2,300 damage to the contractor's equipment, and $1,750
loss of project materials purchased by the contractor. The insurance company is liable for...
-
Answer✅
$1,300
Quiz_________________?
1
, A cost plus contract calls for the contractor to receive direct costs for labor and materials,
and a markup of 20% of direct costs. The contractor is also to receive a bound of 15% of
savings if total cost to the owner is less than $80,000, and a bonus of $1,000 per day if the
project is completed early. Final costs for direct labor and materials are $60,000. The
project is completed 3 days early. What is the total amount due to the contractor? -
Answer✅
Between $75,001 and $80,000
Quiz_________________?
A lump sum contract on a project has a total contract price of $160,000. Retainage has been
held back at 10%. The contractor has received progress payments for 75% of the project.
The contractor submits a request for final payment for the new completed project. The final
payment amount should be for... -
Answer✅
More than $50,000
Quiz_________________?
A non-exempt employee of a contractor covered by the Fair Labor Standards Act works 60
hours during a workweek. The agreement is to pay the employee $400 each week
regardless of the numbers of hours worked. What should be the employee's gross pay for
the worksheet? -
Answer✅
$700.50
Quiz_________________?
A permit is obtained on Friday, May 1. The materials are to be delivered May 8. The
materials are needed when labor begins on May 11. It is estimated that 15 days of labor are
REQUIRED. The crew will work every day, including weekends and holidays. The project is
scheduled to be completed on June 8. How many float days are available for the labor for
this project? -
2