The formula for figuring a BASE asphalt spread rate is
spread rate = thickness x gmm x 43.3
Has the same tolerance or +/-%5 as structural
Do not place friction course until
the shoulder has been dressed and grassed
FC-5 low end ambient air temperature is what?
65F unless the engineer approves use in 60F
If there is a rolling straight edge deficiency found on the friction course layer the contractor and
the engineer can elect to take a no pay instead of remove and replace. That formula is
length of deficiency (+50 ft both sides) x width x depth of layer
What is the minimum amount of RAP in a mix
Maximum 20% by weight of total aggregate
There is a minimum of how many cores even if the lot is terminated?
Three cores
Density makes up how much of pay?
1|Page
, 35%
Airvoids makes up how much of pay?
25%
AC makes up how much of pay?
25%
#200 Sieve makes up how much of pay?
10%
#8 sieve makes up how much of pay?
5%
What is the standard lot size for FC-5?
Always 2000 tons
What is the formula to determine the core location?
2000 x spread rate x 9 / width x tonnage of the core = feet from starting station
What is the application rate for ARMI layers?
0.6 - 0.8 gal/syd
Use the AC(ARB) temperature correction factor
What is the spread rate for the chip spreader?
0.26 to 0.33 ft/syd
with the actual spread rate determined by the engingeer
What is the minimum thickness for asphalt being placed over an ARMI layer?
1 1/2 inches unless plans call for a thicker mat
Where should you stick a thermometer in a truck?