1. The 1970's law that set into place the The Clean Water Act
regulation of stormwater is:
2. Requirements for managing stormwa- NPDES
ter activity on a construction site are
outlined in the following regulation:
3. Which of the following is never an al- Discharge from contaminated groundwater
lowable stormwater discharge from a
construction site?
4. The Notice of termination can filed All construction activity, inside and outside the
when: building, is complete and permanent stabiliza-
tion verified
5. Relative to stormwater permitting, all Submit the notice of termination (NOT)
of the following must occur before con-
struction starts except:
6. Which erosion control best mgmt prac- Vegetation
tice increases water infiltration, dissi-
pates rainfall energy and slows over-
land flow of stormwater
7. Of the following factors that influence Groundcover
erosion rates, the one a contractor has
the most control over is:
8. Temporary stabilization should be im- Immediately on all disturbed areas that are likely
plemented to or will remain inactive for 14-days or more
9. The Primary purpose of a construction To remove sediment from construction site vehi-
exit is cles and minimize trackout