CS302 Final Review Exam Questions and
Answers Graded A+
Who is responsible for approving the Project Management Plan?
A. Project manager and stakeholders
B. Project manager and sponsor
C. Project manager, sponsor and key stakeholders
D. Sponsor only - Correct answer-Project manager, sponsor and key stakeholders
::The Project Management Plan is the master plan from which the project will be
executed. It is the responsibility of all parties (project manager, sponsor, and key
stakeholders) to approve the Project Management Plan.
You are analyzing quality results looking for a relationship between defects and
their causes. Which of the following is the appropriate tool
©COPYRIGHT 2025, ALL RIGHTS RESERVED 1
,A. Tornado diagram
B. Ishikawa diagram
C. Control chart
D. Histogram - Correct answer-B. Ishikawa diagram
::The question is describing cause and effect analysis, for which you would use an
Ishikawa diagram (fishbone)
What is the purpose of a RACI matrix?
A. Displays the relationship between work packages and team members
B. Defines communication channels
C. Authorizes work to begin
D. Speeds up the project schedule
Planning - Human Resources Management - Correct answer-A. Displays the
relationship between work packages and team members
©COPYRIGHT 2025, ALL RIGHTS RESERVED 2
, ::purpose of a RACI matrix is to show the relationship between work packages (or
activities) and team members.
Your change control board (CCB) has just approved a change request. What is the
next thing you should do?
A. Analyze the impact of the change
B. Inform stakeholders of the change approval
C. Update the project plan to reflect the change
D. Manage the project based on the approved change - Correct answer-C. Update
the project plan to reflect the change
::The first thing you should do after a change request is approved is update the
project documents. Once the documents are updated, then you can inform the
stakeholders.
Moreover, some environmental studies suggest that the subsurface in some areas
may be inadequate to sustain the road, which may result in expensive detours being
built around those spots. You are working on your Risk Management Plan. What is
the best way to proceed?
©COPYRIGHT 2025, ALL RIGHTS RESERVED 3
Answers Graded A+
Who is responsible for approving the Project Management Plan?
A. Project manager and stakeholders
B. Project manager and sponsor
C. Project manager, sponsor and key stakeholders
D. Sponsor only - Correct answer-Project manager, sponsor and key stakeholders
::The Project Management Plan is the master plan from which the project will be
executed. It is the responsibility of all parties (project manager, sponsor, and key
stakeholders) to approve the Project Management Plan.
You are analyzing quality results looking for a relationship between defects and
their causes. Which of the following is the appropriate tool
©COPYRIGHT 2025, ALL RIGHTS RESERVED 1
,A. Tornado diagram
B. Ishikawa diagram
C. Control chart
D. Histogram - Correct answer-B. Ishikawa diagram
::The question is describing cause and effect analysis, for which you would use an
Ishikawa diagram (fishbone)
What is the purpose of a RACI matrix?
A. Displays the relationship between work packages and team members
B. Defines communication channels
C. Authorizes work to begin
D. Speeds up the project schedule
Planning - Human Resources Management - Correct answer-A. Displays the
relationship between work packages and team members
©COPYRIGHT 2025, ALL RIGHTS RESERVED 2
, ::purpose of a RACI matrix is to show the relationship between work packages (or
activities) and team members.
Your change control board (CCB) has just approved a change request. What is the
next thing you should do?
A. Analyze the impact of the change
B. Inform stakeholders of the change approval
C. Update the project plan to reflect the change
D. Manage the project based on the approved change - Correct answer-C. Update
the project plan to reflect the change
::The first thing you should do after a change request is approved is update the
project documents. Once the documents are updated, then you can inform the
stakeholders.
Moreover, some environmental studies suggest that the subsurface in some areas
may be inadequate to sustain the road, which may result in expensive detours being
built around those spots. You are working on your Risk Management Plan. What is
the best way to proceed?