1. Which agency primarily enforces construction safety regulations in
New York City?
A) Environmental Protection Agency
B) Department of Buildings
C) Occupational Safety and Health Administration
D) Fire Department
The Department of Buildings (DOB) is responsible for enforcing
construction codes and site safety in NYC.
2. What is the minimum clearance required for scaffolds from
energized power lines?
A) 5 feet
B) 8 feet
C) 10 feet
D) 15 feet
OSHA and DOB regulations require a minimum 10-foot clearance to
prevent electrocution hazards.
3. A Site Safety Manager must be present on a construction site
when:
A) Only during inspections
B) Work involves high-risk operations such as demolition or
excavation
, C) Workers are on lunch break
D) When permits are filed
SSMs are required to supervise high-risk operations, ensuring
compliance with safety regulations.
4. Which of the following is considered a high-risk activity under NYC
construction codes?
A) Painting interior walls
B) Excavation more than 5 feet deep
C) Installing carpeting
D) Cleaning windows
Excavation deeper than 5 feet is classified as high-risk and requires strict
safety measures.
5. What is the maximum allowable slope for a temporary
construction ramp?
A) 5:1
B) 4:1
C) 3:1
D) 2:1
A slope ratio of 4:1 ensures safe movement of personnel and
equipment.
6. Which document must be posted on-site for all construction
projects in NYC?
A) OSHA Annual Report
B) DOB permit
C) Contractor’s insurance policy
D) Building blueprint
, Construction permits must be posted to indicate authorization and
compliance with safety codes.
7. When lifting materials with a crane, the Site Safety Manager must
ensure:
A) Only workers on the ground are watching
B) Materials are lifted without supervision
C) The crane is operated by a licensed operator and the lift is
planned
D) Weather conditions are ignored
Crane operations require licensed operators and careful lift planning to
prevent accidents.
8. The primary purpose of a Site Safety Plan (SSP) is to:
A) Reduce project cost
B) Identify hazards and establish safety procedures
C) Schedule construction tasks
D) Track employee hours
The SSP outlines procedures to protect workers and comply with
regulations.
9. In NYC, fall protection is required for workers at heights of:
A) 4 feet
B) 6 feet
C) 8 feet
D) 10 feet
Regulations require fall protection for work at 6 feet or higher to
prevent serious injuries.