Geschreven door studenten die geslaagd zijn Direct beschikbaar na je betaling Online lezen of als PDF Verkeerd document? Gratis ruilen 4,6 TrustPilot
logo-home
Tentamen (uitwerkingen)

PMP CERTIFICATION EXAM PREPARATION TEST BANK NEWEST 2025/2026 COMPLETE QUESTIONS AND CORRECT DETAILED ANSWERS (VERIFIED ANSWERS) |BRAND NEW VERSION!!

Beoordeling
-
Verkocht
-
Pagina's
723
Cijfer
A+
Geüpload op
03-02-2026
Geschreven in
2025/2026

PMP CERTIFICATION EXAM PREPARATION TEST BANK NEWEST 2025/2026 COMPLETE QUESTIONS AND CORRECT DETAILED ANSWERS (VERIFIED ANSWERS) |BRAND NEW VERSION!!

Instelling
PMP CERTIFICATION
Vak
PMP CERTIFICATION

Voorbeeld van de inhoud

PMP CERTIFICATION EXAM PREPARATION TEST BANK


PMP CERTIFICATION EXAM PREPARATION TEST BANK
NEWEST 2025/2026 COMPLETE QUESTIONS AND
CORRECT DETAILED ANSWERS (VERIFIED ANSWERS)
|BRAND NEW VERSION!!
You are the Project Manager of a project for which a prototype was recently
delivered. The sponsor of the project calls you and gives you an overall estimate
for the project. This form of estimate is known as ____
A. Analogous Estimate
B. Parametric Estimate
C. Heuristic Estimate
D. Three Point Estimate
Correct Option: A

EXPLANATION

Analogous Estimate (also called Top down approach) is a form of Expert
Judgment. It uses estimations from previous similar activities to estimate future
durations. The accuracy of estimates derived using this method depends on the
correctness of historical information, similarity of the historical projects (here a
prototype project), and expert judgment.
A Project Manager who has just been assigned to a new project has been asked by
his sponsor to come up with an initial cost estimate called a Rough Order of
Magnitude (ROM). This would typically fall in which range?
A. -50% to +100%
B. -25% to +75%
C. -10% to +15%
D. -100% to +50%


1|Page

, PMP CERTIFICATION EXAM PREPARATION TEST BANK

Correct Option: B

EXPLANATION

The Rough Order of Magnitude estimate (ROM) is usually done in the initial
stages of the project, when limited information is available. The budgeted
estimate will be in the range of -10% to +25%, and the definitive estimate will be
in the range of -5% to +10%.
In a meeting, the Sponsor has discussed three projects with you: Project A with
Net Present Value of $55,000 and a payback period of 5 years; Project B with Net
Present Value of $95,000; and Project C with payback period of 10 years. He
provides you with additional information about the projects and intends to assign
you as the Project Manager for the selected project. As a Project Manager, you are
NOT expected to:
A. Conduct project selection methods to select one of the three projects discussed
with you by the sponsor to evaluate feasibility of new products and services
B. Proceed to select the project with higher NPV
C. Engage in deceitful practices
D. Participate in the project selection method
Correct Option: C

EXPLANATION

Per the new examination content outline, the project manager participates in
the development of the project charter.
There are three projects A, B, and C. NPV for projects A, B , and C are $50,000, $
80,000, and $ 40,000 respectively. In a meeting, the management unanimously
has chosen projects A and C. What is the opportunity cost of the project?
A. 80000
B. 130000


2|Page

, PMP CERTIFICATION EXAM PREPARATION TEST BANK

C. 90000
D. 0
Correct Option: A

EXPLANATION

Opportunity cost is the cost of giving up the opportunity by selecting a project(s)
over another. Here, Project B is not selected.
A project is in the initiating stage, and the Project Manager is identifying project
communication constraints. Which of the following could be a valid constraint?
A. The project could face high attrition rate
B. Management and customer expect detailed formal status reports on the project
C. Project team members would be required to work from different geographical
locations
D. Many stakeholders of the project would not be able to attend the planned
project kick-off meeting
Correct Option: C

EXPLANATION

Constraints always limit project team options. Option (a) is a known risk, and (b)
and (d) can be addressed under stakeholder management by drawing consensus
on the report format and rescheduling the meeting date.
A Project Manager is responding to a business proposal from an overseas
company. Which of the following should he refer to as a guide to understand the
business practice(s) that are allowed and discouraged?
A. Procurement documents, including contract statement of work
B. Organization policies and procedures
C. Project Charter
D. PMI code of Professional Conduct


3|Page

, PMP CERTIFICATION EXAM PREPARATION TEST BANK

Correct Option: B

EXPLANATION

A Project Manager is an expert in control. Legal (as well as Purchasing) experts
will provide guidance about business decisions one would make in a foreign
country. The PMI® Code of Ethics (1.1.3) states, ®We inform ourselves and
uphold the policies, rules, regulations, and laws that govern our work,
professional, and volunteer activities.®. Option (b) is better.
Which of the following is NOT a project?
A. Campaigning for an election
B. Family Weekend drives to sea coast
C. Writing an autobiography about project management experience
D. Preparing for PMP® examinations
Correct Option: B

EXPLANATION

A project is a temporary endeavor undertaken to create a unique product,
service, or result. Family weekend drive is an ongoing activity and is not a
project.
You have been assigned to a large construction project, and you are in the
"Initiating" process group. You have identified the project stakeholders using a
stakeholder analysis tool and defined the high-level scope of the project. During
these activities, you have identified a key project limitation regarding the project
location. What is the BEST option for you in this situation?
A. Document the project limitation as a project constraint
B. Discuss the project constraint with the project sponsor and the customer
C. Document the project limitation as a project constraint and propose an
implementation approach to the sponsor and customer, if required


4|Page

Geschreven voor

Instelling
PMP CERTIFICATION
Vak
PMP CERTIFICATION

Documentinformatie

Geüpload op
3 februari 2026
Aantal pagina's
723
Geschreven in
2025/2026
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

$23.99
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
SophiaBennettRN Teachme2-tutor
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
24
Lid sinds
1 jaar
Aantal volgers
1
Documenten
2322
Laatst verkocht
1 week geleden
TopGrade Tutor: Expert Psychology, Nursing, Pharmacology & Computer and Math Resources

Welcome to my academic support store, your trusted destination for top-tier homework help and tutoring services! Specializing in key subjects like Psychology, Nursing, Human Resource Management, and Mathematics, I’m dedicated to helping students excel with high-quality, meticulously crafted resources. My mission is to deliver scholarly, reliable content that guarantees excellent grades, earning me a reputation as one of Stuvia’s BEST GOLD RATED TUTORS. Whether you need assistance with quizzes, exams, or detailed study materials, I prioritize your success with a commitment to academic excellence and results you can count on

Lees meer Lees minder
3.9

7 beoordelingen

5
4
4
1
3
0
2
1
1
1

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen