answers
|\
Who is authorized to enforce the provisions of 780 CMR,
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\
review/issue permit applications, issue noticed/orders,
|\ |\ |\ |\ |\
and make required inspections? - CORRECT ANSWERS
|\ |\ |\ |\ |\ |\ |\
✔✔Building official |\
IRC Amendments R104.1 General
|\ |\ |\
Who shall receive and issue permits? - CORRECT
|\ |\ |\ |\ |\ |\ |\ |\
ANSWERS ✔✔Building official |\ |\
IRC Amendments R104.2 Application and Permits
|\ |\ |\ |\ |\
Who shall issue notices and orders? - CORRECT ANSWERS
|\ |\ |\ |\ |\ |\ |\ |\
✔✔Building official
|\ |\
IRC Amendments R104.3
|\ |\
who shall make the required inspections? - CORRECT
|\ |\ |\ |\ |\ |\ |\ |\
ANSWERS ✔✔Building official |\ |\
IRC Amendments R104.4
|\ |\
,A permit is required for work including but not limited to
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\
repairs for substantial cutting of walls - CORRECT
|\ |\ |\ |\ |\ |\ |\ |\
ANSWERS ✔✔IRC Amendments R105.2.2 Repairs |\ |\ |\ |\
The building official shall issue or deny a permit within ___
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\
days of filing - CORRECT ANSWERS ✔✔30 days
|\ |\ |\ |\ |\ |\ |\ |\
IRC Amendments R105.3.1 Action on Application
|\ |\ |\ |\ |\
How many days does a building inspector have to act on
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\
a permit application
|\ |\
a.) 180 days
|\ |\
b.) 90 days
|\ |\
c.) 30 days
|\ |\
d.) 60 days - CORRECT ANSWERS ✔✔c.) 30 days
|\ |\ |\ |\ |\ |\ |\ |\
IRC Amendments R105.3.1 Action on Application
|\ |\ |\ |\ |\
Every permit issued shall become invalid unless the work
|\ |\ |\ |\ |\ |\ |\ |\ |\
authorized by such permit is commended within ___ days. |\ |\ |\ |\ |\ |\ |\ |\
The building official can grant one or more extensions for
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\
periods not more than ____ days - CORRECT ANSWERS
|\ |\ |\ |\ |\ |\ |\ |\ |\
✔✔180 days, 90 days |\ |\ |\
IRC Amendments R105.3.2 Time Limitation on Application
|\ |\ |\ |\ |\ |\
, A permit may be suspended or revoked for all of the
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\
following reasons, except |\ |\
a.) where it is issued in error
|\ |\ |\ |\ |\ |\
b.) on the basis of incomplete information
|\ |\ |\ |\ |\ |\
c.) where issued in violation of jurisdictional ordinance
|\ |\ |\ |\ |\ |\ |\
d.) where other permits by the contractor have been
|\ |\ |\ |\ |\ |\ |\ |\ |\
voided - CORRECT ANSWERS ✔✔d.) where other permits
|\ |\ |\ |\ |\ |\ |\ |\
by the contractor have been voided
|\ |\ |\ |\ |\
IRC Amendments R105.6
|\ |\
Submittal documents consisting of construction |\ |\ |\ |\ |\
documents, and other data shall be submitted in ____ or |\ |\ |\ |\ |\ |\ |\ |\ |\ |\
more sets with each application for a permit - CORRECT
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\
ANSWERS ✔✔two sets |\ |\
IRC Amendments R107.1 Submittal Documents
|\ |\ |\ |\
Townhouse buildings greater than 35,000 square feet |\ |\ |\ |\ |\ |\ |\
require a ______ - CORRECT ANSWERS ✔✔registered
|\ |\ |\ |\ |\ |\ |\
design professional |\
IRC Amendments R107.1.6 Townhouse buildings greater
|\ |\ |\ |\ |\ |\
than 35,000 square feet
|\ |\ |\
On which drawing will you find the building location and
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\
lot lines? - CORRECT ANSWERS ✔✔Site plan/plot plan
|\ |\ |\ |\ |\ |\ |\
IRC Amendments R107.2 Site Plan or Plot Plan
|\ |\ |\ |\ |\ |\ |\