What are the requirements for a new patient room door for
a healthcare occupancy? - Answer-45.5 inches wide &
smoke tight
What are the typical contractor responsibilities during
healthcare construction? - Answer-Operations manuals
Maintenance Manuals
Punch list
TAB Reports
Medical gas verification
What is a TAB report? - Answer-Testing Adjustment
Balancing Report
What are typically NOT a contractor's responsibility during
healthcare construction? - Answer-Final cleaning
Training
,2|Page
What type of rooms require 2 total outdoor air changes? -
Answer-Patient room
NICU
ICU
CCU
Airborne Infection Isolation Room
Protective environment room
Radiology waiting
ED waiting
Triage
What type of rooms require 3 total outdoor air changes? -
Answer-Procedure room
What type of rooms require 4 total outdoor air changes? -
Answer-OR room
Delivery room
What type of rooms require 4 total air changes? - Answer-
Patient room
, 3|Page
What type of rooms require 6 total air changes? - Answer-
NICU
ICU
CCU
What type of rooms require 12 total air changes? -
Answer-Isolation room
Protective environment room
ED Waiting
Radiology waiting
Triage
What type of room requires 20 total air changes? -
Answer-OR room
A patient room requires how many total Outdoor ACH and
how many total ACH? - Answer-2 Total outdoor air
changes
4 Total air changes