In existing facilities, doors that open onto exit corridors
should have 1-3/4 inch solid bonded wood core or be of
construction that resists fire for NOT less than: - Answer-
20 minutes
Total dissolved solids in a cooling tower are regulated by: -
Answer-Variable speed drive fans
What contracts requires a schedule of values when
negotiating? - Answer-Guaranteed maximum price
A project has a budget of $6,600,000. Planning and design
fees are estimated at $700,000 and construction expenses
are estimated at $5,100,000. What is the amount of a 10%
construction contingency? - Answer-580,000
The Joint Commission standards require that an
organization develop and implement a policy to prohibit
smoking except in specified circumstances. The standard
is intended to reduce risks of:
,2|Page
1. Possible adverse effects on care, treatment, and
services to people who smoke
2. Passive smoke to others
3. Fire
4. False alarms - Answer-2, 3, and 4
When planning demolition, construction, or renovation, an
organization selects and implements proper controls to
reduce risk and minimize the impact of these activities on
infection control. Which of the following are proper controls
within the construction area:
1. Providing negative air machines
2. Installing dust barriers
3. Wet-mopping the floors
, 3|Page
4. Ensuring debris-free job site - Answer-2, 3, and 4
A facility is installing an air intake for a medical air
compressor. What is the minimum heights, in ft., at which
this should be located above the ground? - Answer-5
A project estimator is developing a cost estimate for
construction of a new diagnostic imaging wing. The
projected costs are:
Fixed equipment installation charges $700,000
Site isolation $50,000
Annual utilities $425,000
Construction materials $1,200,000
Portable equipment $900,000
Annual depreciation $275,000