Written by students who passed Immediately available after payment Read online or as PDF Wrong document? Swap it for free 4.6 TrustPilot
logo-home
Exam (elaborations)

CDT Practice Exam Study Questions with Correct Answers | Latest Edition

Rating
-
Sold
-
Pages
104
Grade
A+
Uploaded on
10-02-2026
Written in
2025/2026

CDT Practice Exam Study Questions with Correct Answers | Latest Edition 1. What are the 3 parts of a contract? - ANSWER offer, acceptance, consideration 2. Spearin Doctrine - ANSWER A US supreme Court decision in 1918, siding with the contractor who lost a contract despite building in conformance with drawings outcome holds that a contractor is entitled to rely on the construction documents provided by the owners to be sufficient for intended purpose Contractor must show that defects in plans and/or specification were the cause for any unacceptable work or adversely affected the cost or time to complete work. 3. What are the 6 fundamental design approaches - ANSWER site optimization energy performance and conservation water use and conservation materials and resources environmental quality Historic preservation and rehabilitation 4. Construction Documents Contain - ANSWER Procurement requirements Contract Forms Project Forms Conditions of the Contract Specification Drawings Addenda (pre- Contract Revisions) Contract Modification 5. Procurement Documents Contrail - ANSWER Procurement requirements Contract Forms Project Forms Conditions of the Contract Specification Drawings Addenda (pre- Contract Revisions) 6. Typical Project Manuals Contain - ANSWER Procurement requirements Contract Forms Project Forms Conditions of the Contract Specification 7. Contract Requirements contain - ANSWER Contract Forms Project Forms Conditions of the Contract 8. What is a construction schedule - ANSWER developed by the contractor one part of overall project schedule 9. What are the two approaches to project schedules - ANSWER Methods technique Critical path method 10. What is the methods technique - ANSWER establishes required data of occupancy or use identifies all preceding milestones dates by working backwards used when completion data is most important scheduling criterion 11. What is the critical path method - ANSWER determines activates that are dependent upon each other determines longest path for completion of those activates dictate by activates on critical path to completion date 12. What are some due diligence studies that affect site selection - ANSWER hazardous materials evaluation geotechnical investigations environmental studies archeological studies community impact studies 13. What are the two steps to purchase agreements related to site or facility acquisition - ANSWER 1. Buyer submits offer 2. Purchase completed ( contingent upon receipt of evaluation that favors buyer's requirements) 14. What is commissioning - ANSWER The process of verifying and documenting that a building and all of its systems and assemblies are planned, designed, installed, tested, operated, and maintained to meet the owner's project requirements. 15. What are the three types of commissioning - ANSWER total project Systems and equipment Building envelope 16. Total project commissioning - ANSWER begins during project conception, continues through facility management and use documents owner's project requirements verifies criteria are achieved 17. Systems and equipment commissioning - ANSWER includes detailed operation testing ensures readiness for use in facility 18. Building envelope commissioning - ANSWER includes oversight of design and construction assures quality and performance of assemblies 19. What are the three broad principles of commissioning information - ANSWER determining project performance requirements planning the commissioning process document compliance and acceptance

Show more Read less
Institution
Cdt
Course
Cdt

Content preview

CDT Practice Exam Study
Questions with Correct Answers |
Latest Edition
1. What are the 3 parts of a contract? - ANSWER offer, acceptance,
consideration


2. Spearin Doctrine - ANSWER A US supreme Court decision in 1918, siding
with the contractor who lost a contract despite building in conformance with
drawings
outcome holds that a contractor is entitled to rely on the construction documents
provided by the owners to be sufficient for intended purpose
Contractor must show that defects in plans and/or specification were the cause
for any unacceptable work or adversely affected the cost or time to complete
work.


3. What are the 6 fundamental design approaches - ANSWER site
optimization
energy performance and conservation
water use and conservation
materials and resources
environmental quality
Historic preservation and rehabilitation


4. Construction Documents Contain - ANSWER Procurement requirements
Contract Forms
Project Forms

,Conditions of the Contract
Specification
Drawings
Addenda (pre- Contract Revisions)
Contract Modification


5. Procurement Documents Contrail - ANSWER Procurement requirements
Contract Forms
Project Forms
Conditions of the Contract
Specification
Drawings
Addenda (pre- Contract Revisions)


6. Typical Project Manuals Contain - ANSWER Procurement requirements
Contract Forms
Project Forms
Conditions of the Contract
Specification


7. Contract Requirements contain - ANSWER Contract Forms
Project Forms
Conditions of the Contract


8. What is a construction schedule - ANSWER developed by the contractor

,one part of overall project schedule


9. What are the two approaches to project schedules - ANSWER Methods
technique
Critical path method


10.What is the methods technique - ANSWER establishes required data of
occupancy or use
identifies all preceding milestones dates by working backwards
used when completion data is most important scheduling criterion


11.What is the critical path method - ANSWER determines activates that are
dependent upon each other
determines longest path for completion of those activates
dictate by activates on critical path to completion date


12.What are some due diligence studies that affect site selection - ANSWER
hazardous materials evaluation
geotechnical investigations
environmental studies
archeological studies
community impact studies


13.What are the two steps to purchase agreements related to site or facility
acquisition - ANSWER 1. Buyer submits offer
2. Purchase completed ( contingent upon receipt of evaluation that favors
buyer's requirements)

, 14.What is commissioning - ANSWER The process of verifying and
documenting that a building and all of its systems and assemblies are
planned, designed, installed, tested, operated, and maintained to meet the
owner's project requirements.


15.What are the three types of commissioning - ANSWER total project
Systems and equipment
Building envelope


16.Total project commissioning - ANSWER begins during project conception,
continues through facility management and use
documents owner's project requirements
verifies criteria are achieved


17.Systems and equipment commissioning - ANSWER includes detailed
operation testing
ensures readiness for use in facility


18.Building envelope commissioning - ANSWER includes oversight of design
and construction
assures quality and performance of assemblies


19.What are the three broad principles of commissioning information -
ANSWER determining project performance requirements
planning the commissioning process
document compliance and acceptance

Written for

Institution
Cdt
Course
Cdt

Document information

Uploaded on
February 10, 2026
Number of pages
104
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

$11.99
Get access to the full document:

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Get to know the seller
Seller avatar
DrSammuel

Get to know the seller

Seller avatar
DrSammuel TeachmeTutor
Follow You need to be logged in order to follow users or courses
Sold
4
Member since
4 months
Number of followers
0
Documents
730
Last sold
1 month ago
Turning Preparation into Achievement.

Welcome to my study resource hub! This account provides high-quality exam papers with clear and detailed elaborations designed to help students fully understand each topic and pass with confidence.

0.0

0 reviews

5
0
4
0
3
0
2
0
1
0

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions