Geschreven door studenten die geslaagd zijn Direct beschikbaar na je betaling Online lezen of als PDF Verkeerd document? Gratis ruilen 4,6 TrustPilot
logo-home
Tentamen (uitwerkingen)

CAPM FINANCE EXAM | QUESTIONS AND ANSWERS || LATEST EXAM | 100% GRADED A+

Beoordeling
-
Verkocht
-
Pagina's
54
Cijfer
A+
Geüpload op
11-02-2026
Geschreven in
2025/2026

CAPM FINANCE EXAM | QUESTIONS AND ANSWERS || LATEST EXAM | 100% GRADED A+

Instelling
CAPM FINANCE
Vak
CAPM FINANCE

Voorbeeld van de inhoud

CAPM FINANCE EXAM | QUESTIONS
AND ANSWERS || LATEST EXAM
2026-2027 | 100% GRADED A+
5 process groups -ANSWER Initiating
Planning
Executing
Monitoring and Controlling
Closing

ten knowledge areas -ANSWER Integration
Scope
Time
Cost
Quality
HR
Communications
Risk
Procurement
Stakeholder management

total float formula -ANSWER total float = late finish - early finish

normal distribution -ANSWER bell curve - symmetrical distribution - 50% chance of falling
below the mean and 50% chance of falling above the mean (1sigma=68.27%. 2sigma =
95.45%. 3sigma= 99.73%)

triangular distribution -ANSWER when there are 3 possible values w/ equal probability -
distribution is a triangle. A= lowest value, B= highest value, M = most likely value

beta distribution (PERT) -ANSWER triangular distribution w/ more weight given to the
most likely estimate (can be asymmetrical). O = optimistic estimate, ML=most likely
estimate, P=pessimistic estimate

mean for a beta distribution -ANSWER mean = (O + 4ML + P)/6

standard deviation for beta distribution -ANSWER standard deviation = (P-O)/6

statistical sums -ANSWER project mean is the sum of the means of the individual tasks.
project standard deviation is the square root of the project variance

earned value management -ANSWER used to monitor the progress of a project and is an
analytical technique. uses 3 independent values - PV, AC, EV

,planned value (PV) -ANSWER the budget or the portion of the approved cost estimate
planned to be spent during a given period

actual cost (AC) -ANSWER the total of direct and indirect costs incurred in accomplishing
work during a given period

earned value (EV) -ANSWER the budget for the work accomplished in a given period

cost variance (CV) -ANSWER CV = EV - AC

schedule variance (SV) -ANSWER SV = EV - PV

cost performance index (CPI) -ANSWER CPI = EV/AC

schedule performance index (SPI) -ANSWER SPI = EV/PV

positive CV indicates, negative CV indicates -ANSWER costs are below budget, costs are
overrun

positive SV indicates, negative SV indicates -ANSWER a project is ahead of schedule, a
project is behind schedule

CPI greater than 1.0 indicates -ANSWER costs are below budget

SPI greater than 1.0 indicates -ANSWER project is ahead of schedule

CPI less than 1.0 indicates -ANSWER costs are over budget

SPI less than 1.0 indicates -ANSWER a project is behind schedule

estimate at completion (EAC) -ANSWER the amount we expect the total project to cost on
completion and as of the "data date" (time now)

new estimate technique for finding EAC -ANSWER EAC = AC/new estimate for remaining
work

new estimate is most applicable when: -ANSWER the actual performance to date shows
that the original estimates were fundamentally flawed or when they are no longer
accurate because of changes in conditions relating to the project

original estimate technique for finding EAC -ANSWER EAC = AC/(BAC - EV)

original estimate is most applicable when: -ANSWER actual variances to date are seen as
being the exception, and the expectations for the future are that the original estimates
are more reliable than the actual work effort efficiency date

,performance estimate low technique for finding EAC -ANSWER EAC = AC + (BAC -
EV)/CPI or EAC = BAC/CPI

performance estimate low formula is most applicable when: -ANSWER future variances
are projected to approximate the same level as current variances

performance estimate high technique for finding EAC -ANSWER EAC = AC + (BAC - EV) /
(CPI)(SPI)

performance estimate high formula is most applicable when: -ANSWER the project is over
budget and the schedule impacts the work remaining to be completed

BAC -ANSWER budget at completion. the total budgeted cost of all approved activities

ETC -ANSWER estimate to complete - the estimate for completing the remaining work for
a scheduled activity

ETC when past variances are considered to be atypical -ANSWER ETC = BAC - EV

ETC when prior variances are considered to be typical of future variances -ANSWER ETC
= (BAC - EV)/CPI

communications channels -ANSWER channels = (n(n-1))/2. n - number of ppl

rule of seven -ANSWER if 7 or more observations occur in one direction, or a run of 7
observations occurs either above or below the mean, they should be investigated to
determine if they have an assignable cause.

business value -ANSWER the entire value of a business - the total sum of all tangible and
intangible elements

colocation -ANSWER project team members are physically located close to one another in
order to improve communications, working relations, and productivity

constraint -ANSWER a restriction or limitation that may force a certain course of action or
inaction

enterprise environmental factors -ANSWER external or internal factors that can influence
a project's success. includes controllable factors such as the tools used in managing
project within the org, or uncontrollable factors that have to be considered by the project
manager such as market conditions or corporate culture

good practice -ANSWER a specific activity or application of a skill, tool, or technique that
has been proven to contribute positively to the execution of a process

, operations -ANSWER ongoing work performed by ppl, constrained by resources, planned,
executed, monitored, and controlled. unlike a project bc they are repetitive

organizational process assets -ANSWER any formal or informal processes, plans,
policies, procedures, guidelines, and ongoing or historical project info such as lessons
learned, measurement data, project files, and estimates vs actuals

portfolio -ANSWER a collection of programs, projects, and additional work managed
together to facilitate the attainment of strategic business goals

product life cycle -ANSWER the collection of stages that make up the life of a product.
these stages are typically introduction, growth, maturity, and retirement

program -ANSWER a group of related projects managed in a coordinated way

progressive elaboration -ANSWER the iterative process of increasing the level of detail in
a project management plan as greater amounts of information and more accurate
estimates become available

project -ANSWER work performed by ppl, constrained by resources, planned, executed,
monitored and controlled. has a definite beginning and end and creates a unique
outcome

project life cycle -ANSWER the name given to the collection of various phases that make
up a project - make the project easier to control and integrate

project management -ANSWER the ability to meet project requirements by using various
knowledge, skills, tools, and techniques to accomplish project work

project management info system -ANSWER collection of tools, methodologies,
techniques, standards, and resources used to manage a project

stakeholder -ANSWER an individual, group, or organization who may affect by, or
perceive itself to be affected by a decision, activity, or outcome of a project

standard -ANSWER a document that describes rules, guidelines, methods, processes,
and practices that can be used to enhance the chances of success

subproject -ANSWER a component of a project

program management -ANSWER the act of managing a group of related projects in a
coordinated way

project management office (PMO) -ANSWER an additional layer of organization dedicated
to helping project managers

Geschreven voor

Instelling
CAPM FINANCE
Vak
CAPM FINANCE

Documentinformatie

Geüpload op
11 februari 2026
Aantal pagina's
54
Geschreven in
2025/2026
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

$19.49
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Maak kennis met de verkoper
Seller avatar
studymasterstuvia
5.0
(1)

Maak kennis met de verkoper

Seller avatar
studymasterstuvia Walden University
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
3
Lid sinds
10 maanden
Aantal volgers
0
Documenten
890
Laatst verkocht
3 maanden geleden
Master Docs | Trusted Source for All Exams|Study Now

WELCOME TO STUDYMASTERS DOCUMENTS THIS IS PLACE FOR:  VERIFIED EXAMS QUESTIONS AND ANSWERS  ALL EXAMS  LATEST UPDATES  100% GUARANTEED PASS  POCKET FRIENDLY PRICES EXAMS AVAILABLE: • ALL ACLs EXAMS (ALL CHAPTERS) • ALL NURSING EXAMS (ALL CHAPTERS) • ALL CHEMISTRY EXAMS (GCSE, HESI, AP, AQA AND GRADE 10 CHEMISTRY) • ALL BIOLOGY EXAMS • ALL BUSINESS AND BUSINESS LAWS EXAMS • ALL PHYSICS EXAMS • ATI EXAMS • NGN EXAMS • ALL STUDY GUIDE MATERIALS • ALL TEST BANKS • WGU EXAMS • NUR EXAMS ✅ Why Students Choose My Docs: Verified answers and updated content Professionally formatted for quick review Guaranteed accuracy and clarity Affordable prices for premium quality 100% student satisfaction

Lees meer Lees minder
5.0

1 beoordelingen

5
1
4
0
3
0
2
0
1
0

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen