WHO monitors and regulates power demands for the 25 cycle power system - Correct
Answer -Load dispatcher
Who is responsible for the movement of trains within an assigned territory - Correct Answer -
Train dispatchers
Which of the following is an apparatus which serves to increase or decrease voltage - Correct
Answer -Transformer
What class of employee is trained and qualified to provide protection and work on or about
the electrification system - Correct Answer -Class A
Which catenary system is a fixes system of wires suspended between poles and bridges -
Correct Answer -Fixed tension
Which catenary system is a system of wires provided with balance weight tensioning devices
- Correct Answer -Constant tension
Who is in charge of the electrification system within their assigned territory - Correct Answer
-Power director
Class c employees must take and pass an examination on AMT2 how often - Correct Answer
-Every two years
Any occurrence or condition which could affect the electric operation must be reported to -
Correct Answer -Power director/ train dispatcher
What is the voltage in transmission line - Correct Answer -138,000 volts