GUIDE 2026/2027 ACCURATE QUESTIONS
WITH VERIFIED CORRECT ANSWERS ||
ALREADY GRADED A+
<REVISED VERSION>
1. Where do you find approved tack products? - ANSWER ✔ On the FDOT
Approved products list (APL)
2. During night what is the tack you usually use? - ANSWER ✔ PG 52-28 or
an approved emulsion
3. What tack an you use during the day? - ANSWER ✔ Any kind of tack
4. When determining the specification rate for 52-28 tack you do what? -
ANSWER ✔ Multiply the rate by 0.6
5. What is the tack application rate tolerance? - ANSWER ✔ +/- 0.01 gal/syd
6. Step 1 for figuring the tack spread rate - ANSWER ✔ Find the length of the
tack shot
Station - station = ft
7. Step 2 for figuring the tack spread rate - ANSWER ✔ Find the square yards
feet x width / 9 = syds
,8. Step 3 for figuring the tack spread rate - ANSWER ✔ Use the distributor
chart to find the gallons used
start 11/13 - 1319 gal
end 18/14 - 1140 gal
1319 - 1140 = gallons used
9. Step 4 for figuring the tack spread rate - ANSWER ✔ Find the correction
factor on the temperature sheet corresponding to the correct liquid to convert
the gallons to 60F
EX: 160F correction factor = 0.9756
gallons used x correction factor = gallons at 60F
10.Step 5 for figuring the tack spread rate - ANSWER ✔ gallons used at 60F /
syds = tack spread rate
11.What is the application rate for ARMI layers? - ANSWER ✔ 0.6 - 0.8
gal/syd
Use the AC(ARB) temperature correction factor
12.What is the spread rate for the chip spreader? - ANSWER ✔ 0.26 to 0.33
ft/syd
with the actual spread rate determined by the engingeer
13.What is the minimum thickness for asphalt being placed over an ARMI
layer? - ANSWER ✔ 1 1/2 inches unless plans call for a thicker mat
14.Which Statement(s) is true?
A. For fine graded mixes, a type SP-12.5 and a type SP-19.0 can be
placed at 2 inches thick
, B. For coarse graded mixes, a Type SP-12.5 and a Type SP-19.0 can be
placed 3 inches thick
C. For fine graded mixes, a Type SP-9.5 and a Type SP-12.5 can be
placed at 1 1/2 inches thick
D. All the above
E. Both A and C - ANSWER ✔ (D. All the Above) - For fine graded
mixes, a type SP-12.5 and a type SP-19.0 can be placed at 2 inches
thick, For coarse graded mixes, a Type SP-12.5 and a Type SP-19.0
can be placed 3 inches thick, and For fine graded mixes, a Type SP-
9.5 and a Type SP-12.5 can be placed at 1 1/2 inches thick.
15.(T/F:) As long as the project includes milling, it will eliminate reflective
cracking from coming through the new overlay. - ANSWER ✔ True
16.The compactive effort of a rubber-tired roller can be increased most
effectively by:
A. Adding ballast, increasing tire pressure, decreasing coverages
B. Adding ballast, increasing tire pressure, decreasing speed
C. Decreasing ballast, decreasing tire pressure, increasing speed
D. Decreasing ballast, increasing tire pressure, increasing speed
E. None of the above - ANSWER ✔ (B.) Adding ballast, increasing tire
pressure, decreasing speed
17.Which of the following automatic longitudinal screeds controls are
acceptable for all paving courses?
A. Thickness control screws, skid type, and traveling stringline
B. Skid type, traveling stringline, and on-contact averaging ski type
C. Inverted potentiometer
D. Both A and C
E. None of the above - ANSWER ✔ (B.) Skid Type, Traveling
Stringline, and non-Contact averaging ski type
, 18.The density portion of the composite pay for the LOT is based on the PWL
(% within Limits) calculated from:
A. The average density of each sublot compared to the Gmm for that
Sublot
B. The average density of the 20 cores for that Lot compared to the mix
design Gmm
C. The average of 5 cores randomly taken from the Lot
D. Five nuclear density readings for the Sublot - ANSWER ✔ (C.) The
average of 5 cores randomly taken from the Lot
19.In project documents order, which Document(s) has higher authority than
the Supplemental Specifications?
A. Standard Specifications
B. Plans
C. Technical Special Provisions
D. All of the above
E. Both B and C - ANSWER ✔ (E. Both B and C) Plans and Technical
Special Provisions
20.What is the desired tack coat application rate for a milled surface?
A. 0.02-0.08 gal/yd²
B. 0.45 gal/yd²
C. 0.06 gal/yd²
D. 0.08 gal/yd²
E. All the above - ANSWER ✔ (C.) 0.06 gal/yd²
21.Density Testing for acceptance will not be performed on:
A. Shoulder less than 5 feet or less
B. Miscellaneous Asphalt Pavement
C. Cross-overs and intersections less than 1000 feet
D. Acceleration and deceleration lanes less than 1000 feet
E. All the above - ANSWER ✔ (E. All the Above) - Shoulder less than 5
feet or less, Miscellaneous Asphalt Pavement, Cross-overs and