Question 1
Deadline for filing preliminary 20-day notice (late notices are only effective for up to 20 days before filing). A.R.S. § 33-981
Correct Answer
20 days
Question 2
Deadline to file a lien after a "notice of completion" is filed. A.R.S. § 33-993(A)
Correct Answer
60 days
Question 3
Deadline to file a lien after "completion," if a notice of completion is not filed. A.R.S. § 33-993(A
Correct Answer
120 days
Page 1 of 16
,Question 4
Deadline for enforcing a lien (by filing a lawsuit).
Correct Answer
6 months
Question 5
Deadline to dispute a lien after notice of owner's intent to retain payment for the lien from payment to the contractor.
A.R.S. § 33-994
Correct Answer
10 days
Question 6
Deadline for releasing a lien that has been paid in full or following written request, to avoid owing penalties and damages.
A.R.S. § 33-1006
Correct Answer
20 days
Question 7
$1000
Correct Answer
a contractor license is required when the total cost, including materials is more than
Page 2 of 16
, Question 8
ROC
Correct Answer
which state agency has the authority to issue a contractor license
Question 9
ALL OF THE ABOVE
Correct Answer
what is the role of the ROC
Question 10
all of the above
-repairing an hvac
-installing a pool
-wiring a homes electrical circuit
Correct Answer
if you have a B- general license which of the items below must be subcontracted ?
Page 3 of 16