SOLUTIONS GRADED A+
◉ Configuration Status Accounting is the activity used to systematically
manage changes to configuration. Answer: True
-->False
◉ Engineering Change Proposals are used to _____. Answer: -->Change
the configuration baseline of an item
Resolve cost over-runs on a contract
Provide a temporary departure from a specification requirement
Change a contract to reflect a revised delivery schedule
◉ An Engineering Change Proposal (ECP) is _____. Answer: -->A
proposal recommending a change to the design attributes or
configuration of an original item of equipment
A proposal to modify the technical basis for engineering processes
conducted by a contractor under the auspices of the contract
,A proposal to temporarily change the production processes for an item
A proposal to depart from an item's current approved configuration for a
specific number of units or a specified period of time
◉ Which of the following needs to be addressed in the ECP submitted
by the contractor. Answer: -->all these areas listed need to be addressed
Scope of the change
Need or justification for the change
Expected impact of the change
◉ The only authorized medium for directing the modification or the
accomplishment of one-time inspections of systems/equipment is the
_____. Answer: -->Technical directive
Implementing directive
Funding authorization
MIL-HDBK-61A
◉ Configuration Management is not required during the Disposal effort
of the DoD acquisition management framework. Answer: True
-->False
, ◉ Under certain circumstances, temporary certifications for use can be
used to authorize configuration changes or modifications to equipment.
Answer: True
-->False
◉ Determining that a change will likely result in a valid benefit should
be done _____. Answer: -->Before any document is drafted
After funding is requested
Before the final release of the RFP
When the ECP is submitted to the configuration control board
◉ The bulk of the work that occurs during the Submitting step is done
by _____. Answer: -->The contractor
The Procuring Contracting officer
The Government Integrated Product Team (IPT)
The Program Manager
◉ Effectivity refers to _____. Answer: -->the quantity or range of
products targeted for change in the ECP