1. Which of the following best demonstrates the concept of "progressive
design-build" in terms of procurement?
- Correct Answer: Negotiation of final price after team selection
based on qualifications and preliminary design
2. The Design-Builder assumes what type of responsibility regarding errors
and omissions in bridging documents provided by the Owner?
- Correct Answer: Full responsibility for errors and omissions
3. In a Design-Build contract, if the Owner insists on a design specification
rather than a performance specification, which of the following risks
increases significantly for the Owner?
- Correct Answer: Performance failure due to Owner-specified
design
4. What is a key advantage of a Two-Step Best Value procurement over a
Single-Step?
- Correct Answer: Encourages more bidders by reducing workload
in Step 1
,5. Which of the following would most likely trigger a Type 1 differing site
condition claim?
- Correct Answer: Encountering an undocumented utility line
6. Which party typically holds the contractual obligation for obtaining and
paying for permits in a Design-Build delivery model?
- Correct Answer: The Design-Builder
7. In a Design-Build team, the "single point of responsibility" typically refers
to:
- Correct Answer: The Design-Builder
8. Which scenario best reflects a misalignment in expectations during a
progressive design-build process?
- Correct Answer: Owner withholds decision-making authority
from key stakeholders
9. What is the most likely consequence of a poorly defined basis of design
(BOD)?
- Correct Answer: Misinterpretation of performance criteria
10.Under DBIA Standard Form of Agreement, who has the right to direct the
means and methods of construction?
- Correct Answer: The Design-Builder
11.What is the principal challenge in allocating design risk in a Design-Build
project?
- Correct Answer: Transfer of design liability from architect to
design-builder
12.Under DBIA best practices, which of the following is the most important
factor during team selection?
, - Correct Answer: Qualifications and team cohesion
13.A Design-Build project using a bridging approach is most at risk of:
- Correct Answer: Duplicate design effort
14.Which legal doctrine may limit a contractor's liability if a project is built
precisely to Owner-furnished design documents?
- Correct Answer: Spearin Doctrine
15.When is the optimal time to establish the Design-Builder's Guaranteed
Maximum Price (GMP) in a progressive design-build model?
- Correct Answer: At 60-80% design development
16.Which of the following is LEAST likely to be considered a Design-Builder's
risk?
- Correct Answer: Change in Owner leadership
17.If the Owner fails to make timely decisions during the design validation
phase, what is the Design-Builder's best contractual remedy?
- Correct Answer: Issue a change order for delay
18.The primary legal purpose of a teaming agreement in Design-Build
procurement is:
- Correct Answer: To establish terms of collaboration between
design and construction entities
19.Which of the following best reflects the principle of 'design excellence' in
the context of Design-Build?
- Correct Answer: Integrated design solutions aligned with Owner
goals
, 20.In a fixed-price Design-Build contract, cost savings due to innovative
methods usually:
- Correct Answer: Are shared per the contract's incentive
provisions
21.What factor most increases the risk of scope creep in Design-Build?
- Correct Answer: Poorly defined Owner project goals
22.Which is a distinguishing characteristic of a highly effective Owner's criteria
document?
- Correct Answer: Unambiguous functional requirements
23.DBIA advocates for the use of performance-based specifications because
they:
- Correct Answer: Permit innovation by the Design-Builder
24.A Design-Build contract that includes substantial Owner-directed design
elements should:
- Correct Answer: Clearly allocate liability for performance
25.What is the purpose of a validation phase in progressive design-build?
- Correct Answer: To align scope, budget, and performance
expectations
26.In the context of integrated delivery, "design assist" typically refers to:
- Correct Answer: Subcontractors influencing the design for
constructability and cost efficiency
27.What is the primary concern with using prescriptive specifications in a
Design-Build contract?
- Correct Answer: Limits on innovation and design-builder's
responsibility for performance