Written by students who passed Immediately available after payment Read online or as PDF Wrong document? Swap it for free 4.6 TrustPilot
logo-home
Exam (elaborations)

DBIA Design Build Principles Objective Assessment Comprehensive Resource To Help You Ace Includes Frequently Tested Questions With ELABORATED 100% Correct COMPLETE SOLUTIONS Guaranteed Pass First Attempt!! Current Update!!

Rating
-
Sold
-
Pages
61
Grade
A+
Uploaded on
16-02-2026
Written in
2025/2026

DBIA Design Build Principles Objective Assessment Comprehensive Resource To Help You Ace Includes Frequently Tested Questions With ELABORATED 100% Correct COMPLETE SOLUTIONS Guaranteed Pass First Attempt!! Current Update!! 1. Project Delivery System - Correct Answer: How team members are organized, establishes when parties engage, determines roles of parties, and determines sequence of design, procurement, and construction (db, cmar, dbb) 2. Procurement Method - Correct Answer: how team members are selected (QBS, best value, low price, sole source) 3. contracting approach - Correct Answer: how team members are paid (fp, gmp, cost reimbursement, target price, unit price) 4. Design-Bid-Build (DBB) - Correct Answer: linear, sequential process, A/E selected on qualifications, GC selected on low price, design is fully completed without input from GC, A/E acting in owner's interests, with a historically strong bond, process is well-established and understood 5. construction manager at risk - Correct Answer: similar org structure to DBB, construction manager selected by QBS or best value, contractor provides precon services, negotiated gmp contracting approach, open book estimating process, potential to fast track project, construction cost determined before design completed, potential issues over what is reasonably inferable from gmp design documents 6. Design-Build - Correct Answer: The owner contracts with one entity (a person or firm) to provide both design and construction services, designer and contractor have a direct contractual relationship, selected by QBS or best value, wide spectrum of contracting approaches and organizational structures, single point responsibility, owner does not manage designer, owner exposure to claims is significantly reduced 7. Engineer procure construct (epc) - Correct Answer: similar to design build, in industrial and power generation sectors, systems and performance testing are central to scope, contractor will typically perform engineering with its in-house staff, owner has need for single point responsibility, contracts include plant and process performance guarantees, contract items include performance and schedule liquidated damages and limitations of liability 8. Multiple Prime Contracting - Correct Answer: owner contracts with multiple trade contractors, attributes are typically similar to dbb, owner's ability to schedule and coordinate the work 9. Integrated Project Delivery (IPD) - Correct Answer: multi-party agreement - all parties equal, QBS procurement and target pricing contract approach, private sector use (limited at this time), key: owner's ability to accept risk 10. public-private partnership (p3) - Correct Answer: Instead of government building and maintaining major infrastructure (such as highway, water treatment plant), build and maintenance is outsourced to a private company. Opposed by public sector unions. this is not considered a delivery system but its underlying approaches are delivery systems and typically use DB. multiple procurement and contracting approaches 11. shift left - Correct Answer: intense efforts to establish scope early in the process; drives early team formation to include key trade subcontractors; can enable big decisions to be made early, affect project outcomes at lowest cost, establish a need for co-location and collaboration, and compress time during concurrent design and construction 12. traditional design build - Correct Answer: typically two-phase best value procurement with lump sum contract; owner defines project requirements and scope of prescriptive work; use of performance-based technical requirements with limited prescriptive specifications 13. progressive design build - Correct Answer: design and price are progressively developed after the design-builder is under contract; final project cost and schedule commitment is not established as part of the selection process; two phases: preliminary services and final design and construction services 14. criteria documents - Correct Answer: describe the end result 15. bridging documents - Correct Answer: prescribes how to achieve the end result

Show more Read less
Institution
DBIA
Course
DBIA

Content preview

DBIA Design Build Principles Objective Assessment
Comprehensive Resource To Help You Ace 2026-2027
Includes Frequently Tested Questions With ELABORATED
100% Correct COMPLETE SOLUTIONS

Guaranteed Pass First Attempt!!

Current Update!!



1. Project Delivery System - Correct Answer: How team members are
organized, establishes when parties engage, determines roles of parties,
and determines sequence of design, procurement, and construction (db,
cmar, dbb)



2. Procurement Method - Correct Answer: how team members are
selected (QBS, best value, low price, sole source)



3. contracting approach - Correct Answer: how team members are paid
(fp, gmp, cost reimbursement, target price, unit price)



4. Design-Bid-Build (DBB) - Correct Answer: linear, sequential process, A/E
selected on qualifications, GC selected on low price, design is fully
completed without input from GC, A/E acting in owner's interests, with a
historically strong bond, process is well-established and understood



5. construction manager at risk - Correct Answer: similar org structure to
DBB, construction manager selected by QBS or best value, contractor
provides precon services, negotiated gmp contracting approach, open book

, estimating process, potential to fast track project, construction cost
determined before design completed, potential issues over what is
reasonably inferable from gmp design documents



6. Design-Build - Correct Answer: The owner contracts with one entity (a
person or firm) to provide both design and construction services, designer
and contractor have a direct contractual relationship, selected by QBS or
best value, wide spectrum of contracting approaches and organizational
structures, single point responsibility, owner does not manage designer,
owner exposure to claims is significantly reduced



7. Engineer procure construct (epc) - Correct Answer: similar to design
build, in industrial and power generation sectors, systems and performance
testing are central to scope, contractor will typically perform engineering
with its in-house staff, owner has need for single point responsibility,
contracts include plant and process performance guarantees, contract items
include performance and schedule liquidated damages and limitations of
liability



8. Multiple Prime Contracting - Correct Answer: owner contracts with
multiple trade contractors, attributes are typically similar to dbb, owner's
ability to schedule and coordinate the work



9. Integrated Project Delivery (IPD) - Correct Answer: multi-party
agreement - all parties equal, QBS procurement and target pricing contract
approach, private sector use (limited at this time), key: owner's ability to
accept risk

,10.public-private partnership (p3) - Correct Answer: Instead of government
building and maintaining major infrastructure (such as highway, water
treatment plant), build and maintenance is outsourced to a private
company. Opposed by public sector unions. this is not considered a delivery
system but its underlying approaches are delivery systems and typically use
DB. multiple procurement and contracting approaches



11.shift left - Correct Answer: intense efforts to establish scope early in the
process; drives early team formation to include key trade subcontractors;
can enable big decisions to be made early, affect project outcomes at
lowest cost, establish a need for co-location and collaboration, and
compress time during concurrent design and construction



12.traditional design build - Correct Answer: typically two-phase best value
procurement with lump sum contract; owner defines project requirements
and scope of prescriptive work; use of performance-based technical
requirements with limited prescriptive specifications



13.progressive design build - Correct Answer: design and price are
progressively developed after the design-builder is under contract; final
project cost and schedule commitment is not established as part of the
selection process; two phases: preliminary services and final design and
construction services



14.criteria documents - Correct Answer: describe the end result



15.bridging documents - Correct Answer: prescribes how to achieve the
end result

, 16.design bid build paradigm - Correct Answer: prior to bidding, owner
undertakes a process to design the project and all of its details to 100%
complete plans and specs. the owner is therefore responsible for success or
failure of details of the design, and warrants the sufficiency of design to the
contractor. the owner is therefore liable to the contractor for any gaps
between plans and specifications and owner's requirements for project
performance



17.design details responsibility - Correct Answer: the owner should define
its performance requirements and award the contract on the basis of
preliminary design; this makes the design-builder responsible for
completing the design in accordance with the owner's performance
requirements. that also causes the design-builder to warrant the sufficiency
of the design to meet the owner's criteria and the sufficiency of the design
to subcontractors/suppliers that have no design responsibility



18.uniformat - Correct Answer: subdivides project by functional elements,
focuses on systems and assemblies, useful for preliminary information and
early design phases, aligns with BIM models and conceptual estimating



19.masterformat - Correct Answer: subdivides work by results/trades,
focuses on building materials, products, and activities, useful for detailed
information during final design and construction phases, and aligns with
detailed estimating



20.functional requirement - Correct Answer: a specific business need or
behavior as seen by an external user of the system; describe what

Written for

Institution
DBIA
Course
DBIA

Document information

Uploaded on
February 16, 2026
Number of pages
61
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

$13.99
Get access to the full document:

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
NURSINGDICTIONARY Harvard University
Follow You need to be logged in order to follow users or courses
Sold
267
Member since
2 year
Number of followers
87
Documents
2853
Last sold
2 weeks ago
NURSING ENCYCLOPEDIA

As a Career Tutor, I understand the pressure of managing demanding coursework, exams, and practical requirements across multiple disciplines. These professionally organized revision materials are designed to support students in nursing, healthcare administration, business, information systems, Engineering, health, IT, or trade courses management programs by simplifying complex concepts and reinforcing high-yield academic content. The materials are developed to help students: Understand core theories and practical applications across Multiple Disciplines Review exam relevant content aligned with undergraduate and graduate curriculam To Strengthen critical thinking, analytical reasoning, and decision-making skills Save time with clear, structured summaries instead of overwhelming textbooks Prepare efficiently for tests, assignments, case studies, and professional exams Each resource is created with academic standards in mind, integrating real world examples, industry terminology, and evidence based concepts commonly required in professional programs. Whether you are studying nursing fundamentals, healthcare management, information systems, project management, business strategy, Engineering these materials provide focused, reliable support for academic success. These revision guides are ideal for: Nursing and allied health students Healthcare administration and public health students Business, MBA, and management students Information technology and information systems students, engineering, business, IT, or trade courses If you are looking for clear, student-friendly, exam-focused revision materials that support multiple career pathways, these resources are designed to help you study smarter, perform better, and stay confident throughout your academic journey. WISH YOU SUCCESS!!

Read more Read less
4.2

34 reviews

5
18
4
7
3
7
2
1
1
1

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions