Planning process?
Give this one a try later!
human resources
MRP Outputs
Give this one a try later!
1. Recommended production schedule
-tells us what orders and when they should be released to production
2. Recommended purchase schedule
-helps us create purchase orders that identify the quantities of material to
be ordered and when they need to be delivered
, 3. Exception report
-highlights problems and provides reschedule notices about order changes
4. Performance report
-provides metrics on how well production is working
Scheduling
Give this one a try later!
Allocation of resources to activities over time so that demands are met in a
timely and cost-effective manner
Planning vs. Scheduling
Give this one a try later!
Planning- Consists of identifying the key activities in a project and
ordering them in the sequence in which they should be
performed.
*timeframe: months to weeks
*horizon: multiple stages, medium term
*information: aggregate
*objective: money
Scheduling-Consists of putting the plan into the time frame of the calendar
*timeframe: weeks, days, hours
*horizon: one stage, short term
*information: detailed
*objective: time