Control Account Manager (CAM) is responsible for:
Give this one a try later!
allocating resources and planning schedules to accomplish the tasks within
a control account
work/planning packages the CAM develops within their control account
become part of the Integrated Master Schedule (IMS) and the
Performance Measurement Baseline (PMB)
Name two types of WBS
Give this one a try later!
, 1. Program
2. Contract
Name the categories of the WBS hierarchy.
Give this one a try later!
System
System Elements
Enabling System Elements
Program WBS Level I
Give this one a try later!
the entire system and/or program, project, or subprogram
Ex: minuteman ICBM System
LHA Ship System
The WBS integrates technical, cost, and schedule parameters, giving the PM a tool to:
Give this one a try later!
Give this one a try later!
allocating resources and planning schedules to accomplish the tasks within
a control account
work/planning packages the CAM develops within their control account
become part of the Integrated Master Schedule (IMS) and the
Performance Measurement Baseline (PMB)
Name two types of WBS
Give this one a try later!
, 1. Program
2. Contract
Name the categories of the WBS hierarchy.
Give this one a try later!
System
System Elements
Enabling System Elements
Program WBS Level I
Give this one a try later!
the entire system and/or program, project, or subprogram
Ex: minuteman ICBM System
LHA Ship System
The WBS integrates technical, cost, and schedule parameters, giving the PM a tool to:
Give this one a try later!