Develop Project Charter Inputs - CorreCT ansWer-Business documents, Agreements,
Enterprise Enviro. factors, and Org. process assets
Develop Project Charter Tools & Techniques x - CorreCT ansWer-Expert judgement, data
gathering, interpersonal & team skills, and meetings. x
Develop Project Charter Outputs - CorreCT ansWer-Project Charter, Assumption log
Develop PM Plan Inputs - CorreCT ansWer-Proj. charter, outputs from other processes,
Enterprise enviro. factors, and Org. process assets
Develop PM Plan Tool & Techniques - CorreCT ansWer-Expert judgement, data gathering,
interpersonal and team skills, and meetings
Develop PM Plan Outputs - CorreCT ansWer-PM Plan
Direct and Manage Project Work, Inputs - CorreCT ansWer-PM plan, proj. docs, approved
change requests, enterprise enviro. factors, and org. process assets
Direct and Manage Project Work, Tools & Techniques - CorreCT ansWer-Expert judgement,
PMIS, and meetings
Direct and Manage Project Work, Outputs - CorreCT ansWer-Deliverables, work performance
data, issue log, change requests, PM plan updates, proj. docs. updates, and org. process
assets updates
, Manage Project Knowledge, Inputs - CorreCT ansWer-PM plan, proj. docs., deliverables,
enterprise enviro. factors, and org. process assets
Manage Project Knowledge, Tools & Techniques - CorreCT ansWer-Expert judgement,
knowledge management, information management, interpersonal & team skills
Manage Project Knowledge, Outputs - CorreCT ansWer-Lessons learned register, PM plan
updates, and org. process assets updates
Monitor and Control Project Work, Inputs - CorreCT ansWer-PM plan, proj. docs, work
performance information, agreements, enter. enviro. factors, and org. process assets
Monitor and Control Project Work, Tools and Techniques - CorreCT ansWer-Expert
judgement, data analysis, decision making, and meetings
Monitor and Control Project Work, Outputs - CorreCT ansWer-Work performance reports,
change requests, PM plan updates, and proj. docs updates
Perform Integrated Change Control, Inputs - CorreCT ansWer-PM plan, proj. docs, work
performance reports, change requests, enter. enviro. factors, and org. process assets
Perform Integrated Change Control, Tools & Techniques - CorreCT ansWer-Expert judgement,
change control tools, data analysis, decision making, and meetings
Perform Integrated Change Control, Outputs - CorreCT ansWer-Approved change requests,
PM plan updates, and proj. documents updates.
Close Project or Phase, Inputs - CorreCT ansWer-Project charter, PM plan, pro. docs,
accepted deliverables, business docs, agreements, procurement docs, and org. process assets