What part of CARS covers the approval of a type design or change to the type design
of an aeronautical product?
Give this one a try later!
Part V, subpart 21.
How does the CARs numbering system work?
Give this one a try later!
First number is the part, second number is either 0 for a regulation or 2 for
a standard (with some exceptions), third number is subpart, followed by
section, subsection, paragraph, subparagraph, clause, and subclause.
,What is a maintenance schedule?
Give this one a try later!
Repairs and inspections that must follow a schedule (maintenance
schedules are determined by the AMO and usually follow the
manufacturer's maintenance schedule).
Where are definitions found in CARs?
Give this one a try later!
101.01
New regulations must be published how many days prior to their implementation?
Give this one a try later!
60 days.
Air carriers must have a:
Give this one a try later!
Quality assurance programme.
, 625 Appendix C details what?
Give this one a try later!
Out of phase tasks and equipment maintenance requirements.
What is flight time?
Give this one a try later!
The time from the moment an aircraft first moves under its own power for
the purpose of taking off until the moment it comes to rest at the end of
the flight.
Supplemental type certificates are issued when:
Give this one a try later!
Modifications have been made to an aircraft/engine/propellor.
What is an ACA?
Give this one a try later!
Aircraft Certification Authority.
of an aeronautical product?
Give this one a try later!
Part V, subpart 21.
How does the CARs numbering system work?
Give this one a try later!
First number is the part, second number is either 0 for a regulation or 2 for
a standard (with some exceptions), third number is subpart, followed by
section, subsection, paragraph, subparagraph, clause, and subclause.
,What is a maintenance schedule?
Give this one a try later!
Repairs and inspections that must follow a schedule (maintenance
schedules are determined by the AMO and usually follow the
manufacturer's maintenance schedule).
Where are definitions found in CARs?
Give this one a try later!
101.01
New regulations must be published how many days prior to their implementation?
Give this one a try later!
60 days.
Air carriers must have a:
Give this one a try later!
Quality assurance programme.
, 625 Appendix C details what?
Give this one a try later!
Out of phase tasks and equipment maintenance requirements.
What is flight time?
Give this one a try later!
The time from the moment an aircraft first moves under its own power for
the purpose of taking off until the moment it comes to rest at the end of
the flight.
Supplemental type certificates are issued when:
Give this one a try later!
Modifications have been made to an aircraft/engine/propellor.
What is an ACA?
Give this one a try later!
Aircraft Certification Authority.