IFGC) Exam 2026 Questions and
Answers Graded A+
appliance
(Section 101.2.2 Piping Systems) - Correct answer-The IFGC covers gas piping
from the point of delivery to the outlet of the shutoff valves.
this code
(Section 102.8.1 Provisions in referenced codes and standards) - Correct answer-
Where conflicts occur between the provisions of this code and the referenced
standards, the provisions of the __________ ____________ shall apply.
modifications (Section 105.1 Modifications) - Correct answer-Whenever there are
practical difficulties involved in carrying out the provisions of this code, the code
official shall have the authority to grant __________ for individual cases.
©COPYRIGHT 2025, ALL RIGHTS RESERVED 1
,in writing,
reason for disapproval
(Section 105.2 Alternative materials, design and methods of construction and
equipment.) - Correct answer-Where the code official finds that a proposed
alternative material does not comply with the intent of the code provisions, the
code official shall respond __________ __________ stating the __________
__________ _________.
next working
(section 106.1 Where required, Exception) - Correct answer-Where appliance and
equipment replacements and repairs are required to be performed in an emergency
situation, the permit application shall be submitted within the _________
___________ business day of Department of Inspection.
portable
(Section 106.2. Permits not required, Item 1.) - Correct answer-Permits shall not be
required for any _________ heating appliance.
©COPYRIGHT 2025, ALL RIGHTS RESERVED 2
,permit
(Section 106.5 Permit issuance) - Correct answer-The application, construction
documents and other data filed by an applicant for a __________ shall be reviewed
by the code official.
180
(Section 106.5.3 Expiration, Section 106.5.4 Extensions) - Correct answer-Every
permit issued by the code official under the provisions of this code shall expire by
limitation and become null and void if the work authorized is not commenced
within _____ days.
180
(Section 107.2 Retention of construction documents) - Correct answer-One set of
approved construction documents shall be retained by the code official for a period
of not less than _____ days from the date of completion of the permitted work, or
as required by state or local laws.
inspection,
©COPYRIGHT 2025, ALL RIGHTS RESERVED 3
, inspection
(Section 112.1 General) - Correct answer-Construction or work for which a permit
is required shall be subject to _________ by the code official, and such
construction or work shall remain visible and able to be accessed for __________
purposes until approved.
authorized
(Section 110.1 Connection of service utilities) - Correct answer-A person shall not
make connections from a utility, source of energy, fuel or power to any building or
system that is regulated by this code for which a permit is required until
__________ by the code official.
Appliance
(Section 202 General definitions) - Correct answer-Any apparatus or device that
utilizes a fuel or a raw material as a fuel to produce light, heat, power, refrigeration
or air conditioning.
Atmospheric Pressure