Which clause is related to Acquisition? <Correct Answer>> 52.215 - Instructions to
Offerors - Competitive Acquistion
What is considered a contract action? <Correct Answer>> Contract action means any
oral or written action that results in the purchase, rent, or lease of supplies or
equipment, services, or construction.
What is latent defect? <Correct Answer>> is one that is not readily noticeable upon
reasonable inspection at the time of acceptance.
Who accepts the burden of latent defect? <Correct Answer>> The burden is on the
government to prove that defective material and workmanship was the probable cause
of product failure or non-conformance.
Who can you submit a claim to? <Correct Answer>> Contractor claims are submitted
to the KO
,2
What is a claim? <Correct Answer>> a written demand or assertion by one of the
contracting parties seeking (i) payment of a specific sum of money, (ii) adjustment or
interpretation of contract terms, or (iii) other relief arising under or relating to the
contract.
When is written certification for a claim required? <Correct Answer>> When a claim
exceeds $100,000, contractors must provide the following written certification (FAR
33.207).
What are protests? <Correct Answer>> they provide offerors with a tool to challenge
federal contract award decisions.
Who do you file a protest with? <Correct Answer>> The Government Accountability
Office
There is a janitorial contract for 2.8 million dollars for the entire base. What FAR part
would you use? <Correct Answer>> Could be FAR Part 37 Service Contracting or Far
Part 12 Acquisition of Commercial Products and Commercial Services
What common form do you use for a modification? <Correct Answer>> SF-30
What FAR Part is Acquisition Planning? <Correct Answer>> FAR Part 7
,3
What role does the Program Manager plan in Acquistion Planning? -
CORRECTANSWER The PM has overall responsibility of a contract
What is the KO's role in Acquisition Planning? <Correct Answer>> Ensures plan is
implemented and developed.
What are the three phases of a life cycle? <Correct Answer>> Pre-award Phase
Award Phase
Post-award phase
What are the two parts of the Pre-award phase? <Correct Answer>> Develop
Solicitation
Develop offer
Who develops a solicitation? <Correct Answer>> The Government & The Buyer.
Who prepares an offer? <Correct Answer>> The Contractor and the seller
During the post-award phase while the contract is being performed, who has
responsibility for quality? <Correct Answer>> The Seller
What does the award phase involve? <Correct Answer>> Involves all work performed
by the buyer and seller
, 4
The Post-award Phase is also known as <Correct Answer>> Contract Administration
What is the use of a procedure that is inconsistent with the FAR? <Correct Answer>>
Deviation
3 approaches for dealing with OCI issues <Correct Answer>> Avoid
Neutralize
Mitigate
How long should a solicitation be posted for? <Correct Answer>> 10 days
If one offeror submitted a proposal, what does the KO do? <Correct Answer>> KO
must still conduct the source selction process
Improper Business Practices and Personal Conflicts of Interest is what FAR Part? -
CORRECTANSWER FAR Part 3
Organizational conflict of interest is what FAR Part? <Correct Answer>> FAR Part 9
Openness for the contracting officer applies primarily to? <Correct Answer>> The
Acquisition Team
Contractors
CON 3990V Certification Exam Newest 2026
Complete Questions And Correct Detailed
Answers (Verified Answers) |Already Graded
A+
Which clause is related to Acquisition? <Correct Answer>> 52.215 - Instructions to
Offerors - Competitive Acquistion
What is considered a contract action? <Correct Answer>> Contract action means any
oral or written action that results in the purchase, rent, or lease of supplies or
equipment, services, or construction.
What is latent defect? <Correct Answer>> is one that is not readily noticeable upon
reasonable inspection at the time of acceptance.
Who accepts the burden of latent defect? <Correct Answer>> The burden is on the
government to prove that defective material and workmanship was the probable cause
of product failure or non-conformance.
Who can you submit a claim to? <Correct Answer>> Contractor claims are submitted
to the KO
,2
What is a claim? <Correct Answer>> a written demand or assertion by one of the
contracting parties seeking (i) payment of a specific sum of money, (ii) adjustment or
interpretation of contract terms, or (iii) other relief arising under or relating to the
contract.
When is written certification for a claim required? <Correct Answer>> When a claim
exceeds $100,000, contractors must provide the following written certification (FAR
33.207).
What are protests? <Correct Answer>> they provide offerors with a tool to challenge
federal contract award decisions.
Who do you file a protest with? <Correct Answer>> The Government Accountability
Office
There is a janitorial contract for 2.8 million dollars for the entire base. What FAR part
would you use? <Correct Answer>> Could be FAR Part 37 Service Contracting or Far
Part 12 Acquisition of Commercial Products and Commercial Services
What common form do you use for a modification? <Correct Answer>> SF-30
What FAR Part is Acquisition Planning? <Correct Answer>> FAR Part 7
,3
What role does the Program Manager plan in Acquistion Planning? -
CORRECTANSWER The PM has overall responsibility of a contract
What is the KO's role in Acquisition Planning? <Correct Answer>> Ensures plan is
implemented and developed.
What are the three phases of a life cycle? <Correct Answer>> Pre-award Phase
Award Phase
Post-award phase
What are the two parts of the Pre-award phase? <Correct Answer>> Develop
Solicitation
Develop offer
Who develops a solicitation? <Correct Answer>> The Government & The Buyer.
Who prepares an offer? <Correct Answer>> The Contractor and the seller
During the post-award phase while the contract is being performed, who has
responsibility for quality? <Correct Answer>> The Seller
What does the award phase involve? <Correct Answer>> Involves all work performed
by the buyer and seller
, 4
The Post-award Phase is also known as <Correct Answer>> Contract Administration
What is the use of a procedure that is inconsistent with the FAR? <Correct Answer>>
Deviation
3 approaches for dealing with OCI issues <Correct Answer>> Avoid
Neutralize
Mitigate
How long should a solicitation be posted for? <Correct Answer>> 10 days
If one offeror submitted a proposal, what does the KO do? <Correct Answer>> KO
must still conduct the source selction process
Improper Business Practices and Personal Conflicts of Interest is what FAR Part? -
CORRECTANSWER FAR Part 3
Organizational conflict of interest is what FAR Part? <Correct Answer>> FAR Part 9
Openness for the contracting officer applies primarily to? <Correct Answer>> The
Acquisition Team
Contractors