Geschreven door studenten die geslaagd zijn Direct beschikbaar na je betaling Online lezen of als PDF Verkeerd document? Gratis ruilen 4,6 TrustPilot
logo-home
Tentamen (uitwerkingen)

NICET LEVEL III WATER BASED LAYOUT EXAM QUESTIONS AND CORRECT ANSWERS | 100% VERIFIED | LATEST UPDATE 2026/2027 | GRADED A+.

Beoordeling
-
Verkocht
-
Pagina's
24
Cijfer
A+
Geüpload op
21-02-2026
Geschreven in
2025/2026

NICET LEVEL III WATER BASED LAYOUT EXAM QUESTIONS AND CORRECT ANSWERS | 100% VERIFIED | LATEST UPDATE 2026/2027 | GRADED A+. General Conditions - CORRECT ANSWER - What is not included in the technical specification? •contract •specifications •contract drawings - CORRECT ANSWER - Bid documents include? General Conditions - CORRECT ANSWER - Codes, standards, Authority Having Jurisdiction (AHJ), clean-up, safety requirements, barricades, fencing, insurance and bond requirements, ect. Supplementary Conditions - CORRECT ANSWER - Addendums, time schedules, working days allowed, delay agreements, payment schedules Construction Specifications Institute (CSI) - CORRECT ANSWER - Specifications typically use what format? Contractors - CORRECT ANSWER - Construction manager concept is when the owner contracts with the construction manager who oversees ____________ working on the project Design-Build Concept - CORRECT ANSWER - Sometimes referred to as a turn-key type agreement or contract? general contractor - CORRECT ANSWER - Multiple Prime Contractor Method has the intent is eliminate the middleman __________ __________. •architectural/structural contractor •mechanical contractor •electrical contractor - CORRECT ANSWER - Multiple prime contractor method involve more than one prime contractor which consist of? General category and supplementary conditions - CORRECT ANSWER - Contract conditions is divided into two categories which is? Addendum - CORRECT ANSWER - Changes to the contract or other modifications. •up-front payments •progress payments •lump sum - CORRECT ANSWER - Types of payment schedules are? Bidding requirements, sample forms, conditions of the contract and specifications, including general conditions and supplementary conditions - CORRECT ANSWER - What comprises the project manual? •contract itself •contract conditions •specifications •drawings - CORRECT ANSWER - Contract documents include: Preliminary, bid, approval, construction, as-built - CORRECT ANSWER - Drawings have different stages which are? Request for proposal (RFP) - CORRECT ANSWER - Oftentimes a project will begin with a _________. •certified value specialist •owner's representatives •designers and consultants •the construction team •cost estimator •building management staff •third-party (independent) reviewers - CORRECT ANSWER - Valueengineering team typically consist of? •Information gathering •brainstorming •analysis •development •recommendations - CORRECT ANSWER - Value-engineering typically goes through phases which are? Planning stage - CORRECT ANSWER - At what stage does value-engineering provide the most benefit?

Meer zien Lees minder
Instelling
NICET LEVEL III
Vak
NICET LEVEL III

Voorbeeld van de inhoud

NICET LEVEL III WATER BASED LAYOUT EXAM
QUESTIONS AND CORRECT ANSWERS | 100%
VERIFIED | LATEST UPDATE 2026/2027 | GRADED A+.



General Conditions - CORRECT ANSWER - What is not included in the
technical specification?


•contract
•specifications
•contract drawings - CORRECT ANSWER - Bid documents include?


General Conditions - CORRECT ANSWER - Codes, standards, Authority
Having Jurisdiction (AHJ), clean-up, safety requirements, barricades, fencing,
insurance and bond requirements, ect.


Supplementary Conditions - CORRECT ANSWER - Addendums, time
schedules, working days allowed, delay agreements, payment schedules


Construction Specifications Institute (CSI) - CORRECT ANSWER -
Specifications typically use what format?


Contractors - CORRECT ANSWER - Construction manager concept is when
the owner contracts with the construction manager who oversees ____________
working on the project


Design-Build Concept - CORRECT ANSWER - Sometimes referred to as a
turn-key type agreement or contract?

,general contractor - CORRECT ANSWER - Multiple Prime Contractor
Method has the intent is eliminate the middleman __________ __________.


•architectural/structural contractor
•mechanical contractor
•electrical contractor - CORRECT ANSWER - Multiple prime contractor
method involve more than one prime contractor which consist of?


General category and supplementary conditions - CORRECT ANSWER -
Contract conditions is divided into two categories which is?


Addendum - CORRECT ANSWER - Changes to the contract or other
modifications.


•up-front payments
•progress payments
•lump sum - CORRECT ANSWER - Types of payment schedules are?


Bidding requirements, sample forms, conditions of the contract and
specifications, including general conditions and supplementary conditions -
CORRECT ANSWER - What comprises the project manual?


•contract itself
•contract conditions
•specifications
•drawings - CORRECT ANSWER - Contract documents include:


Preliminary, bid, approval, construction, as-built - CORRECT ANSWER -
Drawings have different stages which are?

, Request for proposal (RFP) - CORRECT ANSWER - Oftentimes a project will
begin with a _________.


•certified value specialist
•owner's representatives
•designers and consultants
•the construction team
•cost estimator
•building management staff
•third-party (independent) reviewers - CORRECT ANSWER -
Valueengineering team typically consist of?


•Information gathering
•brainstorming
•analysis
•development
•recommendations - CORRECT ANSWER - Value-engineering typically goes
through phases which are?


Planning stage - CORRECT ANSWER - At what stage does value-engineering
provide the most benefit?


•federal government
•general services administration (GSA)
•large companies - CORRECT ANSWER - Who commonly uses the multiple
prime contractor method?


Owner, architect, general contractor, subcontractor - CORRECT ANSWER -
Traditional method contract uses the typical chain of command which is?

Geschreven voor

Instelling
NICET LEVEL III
Vak
NICET LEVEL III

Documentinformatie

Geüpload op
21 februari 2026
Aantal pagina's
24
Geschreven in
2025/2026
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

$16.99
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF


Ook beschikbaar in voordeelbundel

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
ExcelAcademia2026 Chamberlain College Of Nursing
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
2233
Lid sinds
4 jaar
Aantal volgers
1651
Documenten
9074
Laatst verkocht
15 uur geleden
EXCEL ACADEMIA TUTORS

At Excel Academia Tutoring, You will get solutions to all subjects in both assignments and major exams. Contact me for assistance. Good luck! Well-researched education materials for you. Expert in Nursing, Mathematics, Psychology, Biology etc. My Work has the Latest & Updated Exam Solutions, Study Guides and Notes (100% Verified Solutions that Guarantee Success)

3.7

377 beoordelingen

5
156
4
80
3
70
2
23
1
48

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen