Ram is a new project manager leading the development of a new inventory
management system. He just completed project management training and plans to
follow a step-by-step planning process. Which sequence represents the correct project
planning process? - Answers -Scope, Schedule, Cost
The project team is reviewing the project charter and is creating a work breakdown
structure (WBS). They subdivided the project scope into smaller and more manageable
parts. Which process are they performing? - Answers -Decomposition - is defined as
dividing and subdividing the project scope into smaller and more manageable parts.
A work breakdown structure is organized as follows:
Level 1 - 1 activity
Level 2- 4 activities
Level3-18activities
The project team is preparing to create a project network diagram. How many activities
should be represented in the network diagram? - Answers -18
Only Level 3 activities are represented in a project network diagram.
The project has entered the executing process group. The team performs periodic
audits to ensure the project is executed using prescribed processes and meeting the
mandatory standards. The primary objective is to avoid problems. Which process is
being performed? - Answers -Quality assurance - uses audits to ensure the project is
executed using the prescribed processes and meeting the mandatory standards.
Risk metalanguage is a common method to document a risk. What is the correct risk
metalanguage sequence? - Answers -Cause, Event, Impact
Risk metalanguage uses a cause-event-impact structure to define a risk.
The project management team wants to ensure they are following best practices while
planning the communication management of the project. What two areas must be
included in a project communications management plan? (2 Choices) - Answers -1.
The communications medium is defined in a project communications management plan.
2. Owner
Each communication item is assigned an owner who manages the item.
A number of deliverables for a project are completed: Work performance reports are
used to inform the stakeholders of progress and monitor scope, schedule, cost, and
MANAGEMENT FUNDAMENTALS AND CORE
CONCEPTS
Ram is a new project manager leading the development of a new inventory
management system. He just completed project management training and plans to
follow a step-by-step planning process. Which sequence represents the correct project
planning process? - Answers -Scope, Schedule, Cost
The project team is reviewing the project charter and is creating a work breakdown
structure (WBS). They subdivided the project scope into smaller and more manageable
parts. Which process are they performing? - Answers -Decomposition - is defined as
dividing and subdividing the project scope into smaller and more manageable parts.
A work breakdown structure is organized as follows:
Level 1 - 1 activity
Level 2- 4 activities
Level3-18activities
The project team is preparing to create a project network diagram. How many activities
should be represented in the network diagram? - Answers -18
Only Level 3 activities are represented in a project network diagram.
The project has entered the executing process group. The team performs periodic
audits to ensure the project is executed using prescribed processes and meeting the
mandatory standards. The primary objective is to avoid problems. Which process is
being performed? - Answers -Quality assurance - uses audits to ensure the project is
executed using the prescribed processes and meeting the mandatory standards.
Risk metalanguage is a common method to document a risk. What is the correct risk
metalanguage sequence? - Answers -Cause, Event, Impact
Risk metalanguage uses a cause-event-impact structure to define a risk.
The project management team wants to ensure they are following best practices while
planning the communication management of the project. What two areas must be
included in a project communications management plan? (2 Choices) - Answers -1.
The communications medium is defined in a project communications management plan.
2. Owner
Each communication item is assigned an owner who manages the item.
A number of deliverables for a project are completed: Work performance reports are
used to inform the stakeholders of progress and monitor scope, schedule, cost, and