DBIA EXAM QUESTIONS AND ANSWERS %
ACCURATE.
Which of the following best demonstrates the concept of "progressive design-build" in terms of
procurement? Answer >>> Negotiation of final price after team selection based on
qualifications and preliminary design
The Design-Builder assumes what type of responsibility regarding errors and omissions in
bridging documents provided by the Owner? Answer >>> Full responsibility for errors and
omissions
In a Design-Build contract, if the Owner insists on a design specification rather than a
performance specification, which of the following risks increases significantly for the Owner?
Answer >>> Performance failure due to Owner-specified design
What is a key advantage of a Two-Step Best Value procurement over a Single-Step? Answer
>>> Encourages more bidders by reducing workload in Step 1
Which of the following would most likely trigger a Type 1 differing site condition claim? Answer
>>> Encountering an undocumented utility line
Which party typically holds the contractual obligation for obtaining and paying for permits in a
Design-Build delivery model? Answer >>> The Design-Builder
In a Design-Build team, the "single point of responsibility" typically refers to: Answer >>> The
Design-Builder
,DBIA
Which scenario best reflects a misalignment in expectations during a progressive design-build
process? Answer >>> Owner withholds decision-making authority from key stakeholders
What is the most likely consequence of a poorly defined basis of design (BOD)? Answer >>>
Misinterpretation of performance criteria
Under DBIA Standard Form of Agreement, who has the right to direct the means and methods
of construction? Answer >>> The Design-Builder
What is the principal challenge in allocating design risk in a Design-Build project? Answer >>>
Transfer of design liability from architect to design-builder
Under DBIA best practices, which of the following is the most important factor during team
selection? Answer >>> Qualifications and team cohesion
A Design-Build project using a bridging approach is most at risk of: Answer >>> Duplicate
design effort
Which legal doctrine may limit a contractor's liability if a project is built precisely to Owner-
furnished design documents? Answer >>> Spearing Doctrine
When is the optimal time to establish the Design-Builder's Guaranteed Maximum Price (GMP)
in a progressive design-build model? Answer >>> At 60-80% design development
Which of the following is LEAST likely to be considered a Design-Builder's risk? Answer >>>
Change in Owner leadership
If the Owner fails to make timely decisions during the design validation phase, what is the
Design-Builder's best contractual remedy? Answer >>> Issue a change order for delay
, DBIA
The primary legal purpose of a teaming agreement in Design-Build procurement is: Answer >>>
To establish terms of collaboration between design and construction entities
Which of the following best reflects the principle of 'design excellence' in the context of Design-
Build? Answer >>> Integrated design solutions aligned with Owner goals
In a fixed-price Design-Build contract, cost savings due to innovative methods usually: Answer
>>> Are shared per the contract's incentive provisions
What factor most increases the risk of scope creep in Design-Build? Answer >>> Poorly defined
Owner project goals
Which is a distinguishing characteristic of a highly effective Owner's criteria document? Answer
>>> Unambiguous functional requirements
DBIA advocates for the use of performance-based specifications because they: Answer >>>
Permit innovation by the Design-Builder
A Design-Build contract that includes substantial Owner-directed design elements should:
Answer >>> Clearly allocate liability for performance
What is the purpose of a validation phase in progressive design-build? Answer >>> To align
scope, budget, and performance expectations
In the context of integrated delivery, "design assist" typically refers to: Answer >>>
Subcontractors influencing the design for constructability and cost efficiency
What is the primary concern with using prescriptive specifications in a Design-Build contract?
Answer >>> Limits on innovation and design-builder's responsibility for performance