Geschreven door studenten die geslaagd zijn Direct beschikbaar na je betaling Online lezen of als PDF Verkeerd document? Gratis ruilen 4,6 TrustPilot
logo-home
Tentamen (uitwerkingen)

VA DEQ ESC Inspector Exam Questions and Answers 100% PASS

Beoordeling
-
Verkocht
-
Pagina's
40
Cijfer
A+
Geüpload op
24-02-2026
Geschreven in
2025/2026

VA DEQ ESC Inspector Exam Questions and Answers 100% PASS

Instelling
VA Deq Swm Inspector
Vak
VA deq swm inspector

Voorbeeld van de inhoud

VA DEQ ESC Inspector Exam
Questions and Answers 100%
PASS

VESCP—ANSWER-Virginia Erosion and Sediment Control Program




- Administered by counties/cities (must), towns (may)


- MUST BE APPROVED


Minimum Standard 1—ANSWER-Stabilization




permanent or temporary soil stabilization shall be applied to denuded areas within seven

days after final grade is reached on any portion of the site; temporary soil stabilization shall

be applied within seven days to denuded areas that may not be at final grade but will remain

dormant for longer than 14 days; permanent stabilization shall be applied to areas that are

to be left dormant for more than one year


Site NOT at Final Grade—ANSWER-- stabilize in 14 days


- temporarily seed


- mulch

,- permanently stabilize if dormant > 1 year


Site at Final Grade—ANSWER-- stabilize in 7 days (recommended immediately)


- permanently or temporarily seed and mulch


- mulch/matting/straw


Minimum Standard 2—ANSWER-Stock Piles, Waste and Borrow Areas




during construction, soil stock piles and borrow areas shall be stabilized or protected with

sediment trapping measures




mulch prevents erosion by protecting the surface from raindrop impact and silt fence

intercepts and detains from disturbed areas


Minimum Standard 3—ANSWER-Permanent Vegetation




permanent vegetation cover shall be established on denuded areas not otherwise

permanently stabilized (permanent vegetation shall not be considered established until a

ground cover is achieved that is uniform, mature enough to survive, and will inhibit erosion

there is no % associated with this)




reduce erosion and decrease sediment yield from disturbed area




© 2026 Copyright. All Rights Reserved. This document is
protected by copyright law, Copyrighted By Brittie Donald

,this is the standard used to verify that a site is ready for release of bonds or surety


Minimum Standard 4—ANSWER-First-Step Measures




Sediment basins and traps, perimeter dikes, sediment barriers and other measures intended

to trap sediment shall be constructed as a first step in any land-disturbing activity and shall

be made functional before upslope land disturbance takes place




a certain amount of initial land disturbance may be required to provide access for

equipment to install the perimeter controls, but site clearing and grading should be kept to a

minimum until the perimeter controls are in place




intercepts and detains small amounts of sediment from disturbed areas during construction

operation to prevent sediment from leaving the site and decrease velocity of sheet flows and

low-to-moderate level channel flow


Perimeter Controls—ANSWER-assures that sediment does not leave the perimeter of the

land-disturbing area once site clearing, grading, and construction commences




Examples: silt fences, sediment traps, sediment basins, construction entrance, temporary

diversions, diversions


Minimum Standard 5—ANSWER-Earthen Structure Stabilization

, stabilization measures shall be applied to earthen structures such as dams, dikes, and

diversions immediately after installation




reduce erosion and sedimentation and reduce damage from sediment and runoff to

downstream or off-site areas


Minimum Standard 6—ANSWER-Traps and Basins




sediment traps and basins shall be designed and constructed based upon the total drainage

area (not just disturbed area) to be served by the trap or basin


Sediment Traps—ANSWER-minimum storage capacity shall be 134 cubic yards per acre of

drainage area and shall only control drainage areas less than 3 acres




stone outlet = trap


Sediment Basins—ANSWER-surface runoff from disturbed areas that is comprised of flow

from drainage areas greater than or equal to 3 acres shall be controlled by a basin; minimum

storage capacity of a sediment basin shall be 134 cubic yards per acre of drainage area; the

outfall system shall, at a minimum, maintain the structural integrity of the basin during a 25-

year storm of 24-hour duration; runoff coefficients used in runoff calculations shall

correspond to a bare earth condition or those conditions expected to exist while the

sediment basin is utilized.


Sediment Trapping Devises—ANSWER-1. place near the lowest drainage points of a project

© 2026 Copyright. All Rights Reserved. This document is
protected by copyright law, Copyrighted By Brittie Donald

Geschreven voor

Instelling
VA deq swm inspector
Vak
VA deq swm inspector

Documentinformatie

Geüpload op
24 februari 2026
Aantal pagina's
40
Geschreven in
2025/2026
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

$14.99
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
EmilyCharlene Teachme2-tutor
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
498
Lid sinds
2 jaar
Aantal volgers
138
Documenten
22999
Laatst verkocht
1 week geleden
Charlene\'s Scholastic Emporium.

Your Actual and Virtual Exam Tests Excellent Tutor.

3.7

112 beoordelingen

5
51
4
18
3
16
2
7
1
20

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen