Geschreven door studenten die geslaagd zijn Direct beschikbaar na je betaling Online lezen of als PDF Verkeerd document? Gratis ruilen 4,6 TrustPilot
logo-home
Tentamen (uitwerkingen)

CAPM 2026 QUESTIONS AND - ANSWERS | A+ GRADED | WITH EXPERT SOLUTIONS

Beoordeling
-
Verkocht
-
Pagina's
57
Cijfer
A+
Geüpload op
26-02-2026
Geschreven in
2025/2026

CAPM 2026 QUESTIONS AND - ANSWERS | A+ GRADED | WITH EXPERT SOLUTIONS

Instelling
CAPM
Vak
CAPM

Voorbeeld van de inhoud

CAPM 2026 QUESTIONS AND -
ANSWERS | A+ GRADED | WITH EXPERT
SOLUTIONS
5 process groups - - ANSWER Initiating
Planning
Executing
Monitoring and Controlling
Closing

ten knowledge areas - - ANSWER Integration
Scope
Time
Cost
Quality
HR
Communications
Risk
Procurement
Stakeholder management

total float formula - - ANSWER total float = late finish - early finish

normal distribution - - ANSWER bell curve - symmetrical distribution - 50% chance of
falling below the mean and 50% chance of falling above the mean (1sigma=68.27%.
2sigma = 95.45%. 3sigma= 99.73%)

triangular distribution - - ANSWER when there are 3 possible values w/ equal
probability - distribution is a triangle. A= lowest value, B= highest value, M = most likely
value

beta distribution (PERT) - - ANSWER triangular distribution w/ more weight given to the
most likely estimate (can be asymmetrical). O = optimistic estimate, ML=most likely
estimate, P=pessimistic estimate

mean for a beta distribution - - ANSWER mean = (O + 4ML + P)/6

standard deviation for beta distribution - - ANSWER standard deviation = (P-O)/6

statistical sums - - ANSWER project mean is the sum of the means of the individual
tasks. project standard deviation is the square root of the project variance

,earned value management - - ANSWER used to monitor the progress of a project and
is an analytical technique. uses 3 independent values - PV, AC, EV

planned value (PV) - - ANSWER the budget or the portion of the approved cost
estimate planned to be spent during a given period

actual cost (AC) - - ANSWER the total of direct and indirect costs incurred in
accomplishing work during a given period

earned value (EV) - - ANSWER the budget for the work accomplished in a given period

cost variance (CV) - - ANSWER CV = EV - AC

schedule variance (SV) - - ANSWER SV = EV - PV

cost performance index (CPI) - - ANSWER CPI = EV/AC

schedule performance index (SPI) - - ANSWER SPI = EV/PV

positive CV indicates, negative CV indicates - - ANSWER costs are below budget,
costs are overrun

positive SV indicates, negative SV indicates - - ANSWER a project is ahead of
schedule, a project is behind schedule

CPI greater than 1.0 indicates - - ANSWER costs are below budget

SPI greater than 1.0 indicates - - ANSWER project is ahead of schedule

CPI less than 1.0 indicates - - ANSWER costs are over budget

SPI less than 1.0 indicates - - ANSWER a project is behind schedule

estimate at completion (EAC) - - ANSWER the amount we expect the total project to
cost on completion and as of the "data date" (time now)

new estimate technique for finding EAC - - ANSWER EAC = AC/new estimate for
remaining work

new estimate is most applicable when: - - ANSWER the actual performance to date
shows that the original estimates were fundamentally flawed or when they are no longer
accurate because of changes in conditions relating to the project

original estimate technique for finding EAC - - ANSWER EAC = AC/(BAC - EV)

,original estimate is most applicable when: - - ANSWER actual variances to date are
seen as being the exception, and the expectations for the future are that the original
estimates are more reliable than the actual work effort efficiency date

performance estimate low technique for finding EAC - - ANSWER EAC = AC + (BAC -
EV)/CPI or EAC = BAC/CPI

performance estimate low formula is most applicable when: - - ANSWER future
variances are projected to approximate the same level as current variances

performance estimate high technique for finding EAC - - ANSWER EAC = AC + (BAC -
EV) / (CPI)(SPI)

performance estimate high formula is most applicable when: - - ANSWER the project is
over budget and the schedule impacts the work remaining to be completed

BAC - - ANSWER budget at completion. the total budgeted cost of all approved
activities

ETC - - ANSWER estimate to complete - the estimate for completing the remaining
work for a scheduled activity

ETC when past variances are considered to be atypical - - ANSWER ETC = BAC - EV

ETC when prior variances are considered to be typical of future variances - - ANSWER
ETC = (BAC - EV)/CPI

communications channels - - ANSWER channels = (n(n-1))/2. n - number of ppl

rule of seven - - ANSWER if 7 or more observations occur in one direction, or a run of 7
observations occurs either above or below the mean, they should be investigated to
determine if they have an assignable cause.

business value - - ANSWER the entire value of a business - the total sum of all tangible
and intangible elements

colocation - - ANSWER project team members are physically located close to one
another in order to improve communications, working relations, and productivity

constraint - - ANSWER a restriction or limitation that may force a certain course of
action or inaction

enterprise environmental factors - - ANSWER external or internal factors that can
influence a project's success. includes controllable factors such as the tools used in
managing project within the org, or uncontrollable factors that have to be considered by
the project manager such as market conditions or corporate culture

, good practice - - ANSWER a specific activity or application of a skill, tool, or technique
that has been proven to contribute positively to the execution of a process

operations - - ANSWER ongoing work performed by ppl, constrained by resources,
planned, executed, monitored, and controlled. unlike a project bc they are repetitive

organizational process assets - - ANSWER any formal or informal processes, plans,
policies, procedures, guidelines, and ongoing or historical project info such as lessons
learned, measurement data, project files, and estimates vs actuals

portfolio - - ANSWER a collection of programs, projects, and additional work managed
together to facilitate the attainment of strategic business goals

product life cycle - - ANSWER the collection of stages that make up the life of a
product. these stages are typically introduction, growth, maturity, and retirement

program - - ANSWER a group of related projects managed in a coordinated way

progressive elaboration - - ANSWER the iterative process of increasing the level of
detail in a project management plan as greater amounts of information and more
accurate estimates become available

project - - ANSWER work performed by ppl, constrained by resources, planned,
executed, monitored and controlled. has a definite beginning and end and creates a
unique outcome

project life cycle - - ANSWER the name given to the collection of various phases that
make up a project - make the project easier to control and integrate

project management - - ANSWER the ability to meet project requirements by using
various knowledge, skills, tools, and techniques to accomplish project work

project management info system - - ANSWER collection of tools, methodologies,
techniques, standards, and resources used to manage a project

stakeholder - - ANSWER an individual, group, or organization who may affect by, or
perceive itself to be affected by a decision, activity, or outcome of a project

standard - - ANSWER a document that describes rules, guidelines, methods,
processes, and practices that can be used to enhance the chances of success

subproject - - ANSWER a component of a project

program management - - ANSWER the act of managing a group of related projects in a
coordinated way

Geschreven voor

Instelling
CAPM
Vak
CAPM

Documentinformatie

Geüpload op
26 februari 2026
Aantal pagina's
57
Geschreven in
2025/2026
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

$18.49
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Maak kennis met de verkoper
Seller avatar
catherinenmuchira123

Maak kennis met de verkoper

Seller avatar
catherinenmuchira123 teach me 2 tutor
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
4
Lid sinds
2 maanden
Aantal volgers
0
Documenten
192
Laatst verkocht
2 weken geleden

0.0

0 beoordelingen

5
0
4
0
3
0
2
0
1
0

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen