What is a Contracting Officer Representative? - ANSWER -A
technical representative that is appointed by the contracting
officer through a designation letter
The COR may be asked to review the cost proposal and the
proposed Basis of
Estimate (BOE) and to assist the KO in determining the
reasonableness of the
proposed amounts. -
ANSWER -True
Common causes of a constructive change include: -
ANSWER -All these
answers are
correct
When there is a difference of opinion between the COR and the
contractor on a
specification within the contract, the COR should direct
the contractor to
perform in accordance with the COR's interpretation. -
ANSWER -False
,After award of the contract, the post-award conference is a
good place to ensure that the government and the contractor
have a common understanding of the contractual requirements.
- ANSWER -True
Past performance assessments include input from the
__________. - ANSWER
-All the answers are
correct
The inspection clause for ____________contracts allows for
the contractor to
charge the cost of rework to the government. - ANSWER -Cost
Reimbursement
The Contracting Officer's Representative's role in inspection is
to determine whether the completed supplies and services
conform to what the government ordered and can be accepted.
- ANSWER -True
The COR may officially accepts supplies and services for the
Government. -
ANSWER -
True
Only the government input is recorded on past performance
in the Contractor
, Performance Assessment Record System. -
ANSWER -False
Under the Prompt Payment clause, unless specifically
prohibited by the contract, the contractor is entitled to payment
for accepted partial deliveries of supplies or partial
performance of services that comply with all applicable
contract requirements and for which prices can be calculated
from the contract terms. - ANSWER -True
Disposition of Government property must be conducted in
accordance with __. -
ANSWER -All the responses are
correct
The government's policy is for contractors to provide all of their
own general purpose equipment. However, on a base or
installation or in a contingency contracting environment,
equipment may be accountable under the contract as
Government Property. - ANSWER -True
The Contracting Officer's Representative has authority to
approve overtime
requests from the contractor. -
ANSWER -False
A COR will typically use a ____________ to document the
inspection and