The president of a software company remarks in a speech that new
technologically advanced software will be available in one year. This is
an example of reducing project duration caused by
Ans: Imposed project deadlines
Adverse weather, design flaws, and equipment breakdown can create
negative slack. This is an example of reducing project duration caused
by:
Ans: Unforeseen project delays
Which of the following is not considered a project indirect cost?
Ans: Equipment
Low-cost, realistic, efficient methods for completing an activity under
normal conditions are supported by ____ time.
Ans: Normal
The shortest possible time an activity can be completed realistically is
called ___ time.
All rights reserved © 2025/ 2026 |
, Page |2
Ans: Crash
____ costs are incurred when completing an activity in its realistically
shortest time.
Ans: Crash
Cost slope can be determined by dividing the
Ans: Rise by the run
Which of the following correctly calculates an activity's cost slope?
Ans: (crash cost-normal cost)/(normal time-crash time)
The optimum duration for a project is at the point where:
Ans: Total project costs are the lowest
Creating a Project Cost-Duration graph is useful:
Ans: A) During the pre-project planning phase
B) After the project has begun
If a network has several critical or near-critical paths it is deemed to be: