202
Updated!!!
1. 1) Exemplary Performance credits can be achieved b. Innovation
in which LEED rating system category?
a. Materials and Resources
b. Innovation
c. Sustainable Sites
d. Water Efciency
2. 2. The term "stakeholder" encompasses more than a. Those who must live with
just decision makers and includes: the decisions and those who
a. Those who must live with the decisions and those must carry them out.
who must carry them out.
b. Everyone who has a nancial stake in the building.
c. Everyone who is on the company payroll.
d. Those members of the community who are not
af liated with the company but are affected by its
decisions.
3. 3. What is the most critical impact category out of a. Reverse
the seven, meaning the largest environmental im- Contribution to Global
pact, as determined by USGBC? Climate Change
a. Reverse Contribution to Global Climate Change
b. Protect, Enhance, and Restore Biodiversity and
Ecosystem Services c. Protect and Restore Water
Resources
d. Enhance Individual Human Health and Well-Be-
ing
4. 4. The total land area of a project site covered by
buildings, streets, parking areas, and other typically c. Development footprint
impermeable surfaces constructed as part of the
project is called the:
, LEED GA Exam Correctly Solved Questions And Answers {100% Correct}
202
Updated!!!
a. Building envelope
b. Project site boundary
c. Development footprint
d. Project to site ratio
5. 5. Pervious paving areas support which two Sustain- a. Reduce heat island ettect
able Sites (SS) goals? (select two) e. Reduce rainwater runott
a. Reduce heat island effect
b. Eliminate light pollution
c. Improve ground water quality
d. Protect open space
e. Reduce rainwater runoff
6. 6. The Energy Policy Act of 1992 (EPAct 1992) es- c. 1.6 gpf
tablishes which ush rate as the baseline water con-
sumption for water closets?
a. 0.25 gpf
b. 0.6 gpf
c. 1.6 gpf
d. 1.6 gpm
7. 7. A charrette is: c. The process brings to-
a. Generally held at the end of the project gether the project team with
b. The process of bringing in the design team only stakeholders and outside ex-
for focused conversations perts for creative
c. The process brings together the project team with thinking and collaboration
stakeholders and outside experts for creative
thinking and collaboration
d. A gathering of LEED APs for a general discussion
on sustainability
8.
, LEED GA Exam Correctly Solved Questions And Answers {100% Correct}
202
Updated!!!
8. When applying systems thinking to designing d. Both the individual ele-
building and communities, we must understand: ments of the system and their
a. Systems are always simple and self-contained relationships to each other as
b. Most systems are actually systems within sys- a whole
tems
c. Unchecked, positive feedback loops can create
chaos in a system
d. Both the individual elements of the system and
their relationships to each other as a whole
9. 9. ASHRAE 55 relates to: c. Thermal comfort of indoor
a. Minimum energy performance occupants
b. Mechanically ventilated spaces
c. Thermal comfort of indoor occupants
d. Naturally ventilated spaces
10. 10. Two strategies to promote sustainable purchas- b. Develop a sustainable ma-
ing during design and operations are: (select two) terials policy outlining the
a. Provide all employees with a free hybrid car after goals, thresholds, and proce-
one year of employment. dures for
b. Develop a sustainable materials policy outlining procurement of ongoing
the goals, thresholds, and procedures for consumables and durable
procurement of ongoing consumables and durable goods.
goods.
c. Institute a green signage policy to put up signs e. Specify green custodial
reminding employees to turn off lights and products that meet Green
computers, compost their food waste, and to recy- Seal, Environmental Choice or
cle glass, aluminum, and paper. EPA standards to protect in-
d. Provide employees incentives such as vacation door environmental quality.
hours for purchasing products with recycled
content and low VOCs.