1. What is at the core of the integrative process? Collaborative Team Mem-
Choose one: bers
Working toward individual goals
Upfront cost based decision making
Collaborative team members
Linear planning
2. A LEED project is in the predesign phase, and a previ- Restoring compacted soils
ously developed site has already been selected. The and revegetating
team wants to protect or restore habitat. Which of
the following strategies should they consider?
Choose one
Increasing the floor to area ratio of the building
Restoring compacted soils and revegetating
Implementing a construction activity pollution plan
Using pervious paving materials for the parking area
3. What type of plants should be used on a green roof Native Plants
to promote biodiversity?
Choose one
Tall plants that provide shade
Monocultures
Plants with high watering needs
Native plants
4. Which of the following is NOT a strategy to reduce Maximize the building foot-
construction waste? print
Choose one
Recycle materials
Sell unused materials
, LEED GA EXAM SOLVED CORRECTLY TO SCORE A+ 2026 UPDATE!!!
Use salvaged materials
Maximize the building footprint
5. What is the purpose of having a LEED AP on a pro- To streamline the LEED
ject? process
Choose one
To serve as the project administrator
To streamline the LEED process
To submit all project data
For building commissioning
6. What type of water is rainwater? nonpotable water
Choose one
Blackwater
Graywater
Nonpotable water
Potable water
7. Indoor water use reductions require projections Occupants' usage
based on which of the following:
Choose one
The number of fixtures installed
The gross area of the building
The cost of potable water
Occupants' usage
8. To transform the way buildings and communities are USGBC'S Mission
designed, built, and operated, enabling
an environmentally and socially responsible,
healthy, and prosperous environment that im-
proves
the quality of life' denotes which of the following:
Choose one
, LEED GA EXAM SOLVED CORRECTLY TO SCORE A+ 2026 UPDATE!!!
The purpose of LEED Online
USGBC's mission
USGBC's 2013-2015 strategic plan
USGBC's vision
9. Which greenhouse gas is produced in landfills as a Methane
result of solid waste disposal?
Choose one
Methane
CO2
Radon
NH3
10. Which of the following project team members is re- The commissioning authori-
sponsible for verifying and documenting ty
that a building and all of its systems and assemblies
are planned, designed, installed, tested, operated,
and maintained to meet the owner's project require-
ments?
Choose one
The commissioning authority
The mechanical engineer
The project administrator
The LEED project reviewer
11. REACH Optimization would be used in which of the MR category
following credit categories?
Choose one
Materials and Resources
Indoor Environmental Quality
Location and Transportation
Energy and Atmosphere