API 510 PREP EXAM 2026 ALL QUESTIONS
AND CORRECT DETAILED ANSWERS
ALREADY A GRADED WITH EXPERT
FEEDBACK |NEW AND REVISED
Substituting NDE procedures for a pressure test after major repair may
be done only after:
API 510 5.8.8.1 - ANSWER- The engineer and inspector have approved.
An example of vessels not covered by API 510 are:
API 510 1.1.1 - ANSWER- Vessels officially retired from service and
abandoned in place.
ACFM is an acronym for:
ASME SEC 5 Article 15 - ANSWER- Alternating Current Field
Measurement
A pneumatic testing precedure should be developed by whom before
conducting the test?
API 510 5.8.6 - ANSWER- Engineer
A signal of discontinuity in the material under nondestructive
examination is considered:
API RP 577 3.1.36 - ANSWER- Indication
, 2|Page
In what type of service should vessels be evaluated for potential fatigue
cracking failures and have appropriate inspections planned?
API 510 5.4.4 - ANSWER- Cyclic Service
Corrosion and other damage identified during inspections and
examinations must be characterized, sized, and evaluated per Section 7
(Inspection Data Evaluation, Analysis, and Recording) with deviations
from the inspection plan being approved by whom?
API 510 5.5.1 - ANSWER- Inspector or Engineer
Inspection tasks typically associated with hot tapping or welding on in-
service equipment should include:
API 577 11.2.5 - ANSWER- Positive Metal Identification (PMI)
Any repair welding should be performed according to a procedure
accepted by the:
API 510 8.1.1 - ANSWER- Inspector or Engineer
Welding of carbon steel with carbon contents over 0.30%
API 510 8.1.5 - ANSWER- May need special attention and preheating to
avoid weld cracking.
Inspector recommendations can be changed or deleted after review by
whom?