Requirements Certification Exam
Preparation
Question 1. **Which document does the Special Inspector review first to determine required
inspections?**
A) Construction Schedule
B) Statement of Special Inspections (SSI)
C) Contractor’s Safety Plan
D) Owner’s Project Manual
Answer: B
Explanation: The SSI lists all required special inspections, making it the primary reference for the
inspector.
Question 2. **What must the Special Inspector verify before any inspection begins?**
A) Contractor’s insurance coverage
B) Approval of project plans and specifications by the building official
C) Availability of subcontractors
D) Completion of the contractor’s safety orientation
Answer: B
Explanation: Verification ensures that the construction documents have been legally approved,
establishing the baseline for compliance.
Question 3. **During coordination, the Special Inspector should primarily communicate with
which party to clarify inspection requirements?**
A) Project Owner
B) Building Official
C) Registered Design Professional (RDP)
D) General Contractor’s foreman
, [GRSIGR] GR GR Special Inspector General
Requirements Certification Exam
Preparation
Answer: C
Explanation: The RDP prepares the SSI and can interpret design intent, making them the key
source for clarification.
Question 4. **Which action is the Special Inspector prohibited from performing on a
construction site?**
A) Issuing a daily inspection report
B. Notifying the contractor of a non‑conforming item
C) Stopping work until the issue is corrected
D. Recording test results in a log
Answer: C
Explanation: Special Inspectors report deficiencies but do not have authority to stop work; that
authority rests with the building official.
Question 5. **What distinguishes a “continuous” inspection from a “periodic” inspection?**
A) Continuous inspections occur only at the project start.
B) Continuous inspections require the inspector to be present throughout the activity.
C) Periodic inspections are performed daily.
D) Periodic inspections are optional.
Answer: B
Explanation: Continuous inspections mandate the inspector’s presence for the entire duration
of the activity, whereas periodic inspections are scheduled at intervals.
Question 6. **Which of the following is a responsibility of the Special Inspector regarding
material approvals?**
, [GRSIGR] GR GR Special Inspector General
Requirements Certification Exam
Preparation
A) Approving material substitutions without RDP input
B) Verifying that material labels match manufacturer certificates
C) Authorizing design changes on site
D. Issuing final occupancy permits
Answer: B
Explanation: The inspector must confirm that on‑site materials correspond to the approved
documentation, but cannot approve changes independently.
Question 7. **Who holds the legal authority to enforce the Building Code on a construction
project?**
A) Project Owner
B) Registered Design Professional (RDP)
C) Building Official
D) Special Inspector
Answer: C
Explanation: The building official is the statutory authority responsible for code enforcement
and issuing approvals.
Question 8. **Which statement accurately reflects the Building Official’s “Approval to Proceed”
authority?**
A) It can be delegated to the Special Inspector.
B) It is required before any construction activity begins.
C) It is optional for minor work.
D. It is only needed after final inspection.
Answer: B
, [GRSIGR] GR GR Special Inspector General
Requirements Certification Exam
Preparation
Explanation: No construction may commence without the building official’s formal “Approval to
Proceed,” regardless of project size.
Question 9. **The Project Owner must ensure independence between the inspector and which
other party?**
A) Material supplier
B) Contractor
C) Local fire department
D. Sub‑contractor
Answer: B
Explanation: Independence prevents undue influence from the contractor, preserving the
objectivity of the inspection process.
Question 10. **Which document is prepared by the RDP to initiate the special inspection
program?**
A) Construction Safety Plan
B) Statement of Special Inspections (SSI)
C) Contractor’s Bid Proposal
D. Owner’s Budget Report
Answer: B
Explanation: The RDP drafts the SSI, which outlines the scope, frequency, and methods of
required inspections.
Question 11. **What must the Contractor provide to facilitate the Special Inspector’s work?**
A) Daily weather reports